Assessment Year | 2001 |
---|---|
Principal Product | Food Texturizing Ingredients |
NAICS |
n/a
|
SIC | 2099: Food Preparations, Not Elsewhere Classified |
Sales Range | $5 M to 10M |
# of Employees | 21 |
Plant Area |
32,411
ft2
|
Annual Production | 3,500,000
lb
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Illinois |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $55,025 | 1,286,400 |
kWh
|
$0.043 |
Electricity Demand | $29,845 | 3,206 |
kW-mo/yr
|
$9.31 |
Electricity Fees | $9,894 | - |
|
- |
Natural Gas | $243,193 | 37,493 |
MMBtu
|
$6.49 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $40,025 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $12,419 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4224: Upgrade controls on compressors | $8,978 | $9,500 | n/a |
$6,723
157,081
kWh
|
$2,255
-
kW-mo/yr
|
- | - | - | - |
02 | 2.4133: Use most efficient type of electric motors | $3,215 | $4,660 |
$2,445
57,146
kWh
|
$770
-
kW-mo/yr
|
- | - | - | - | |
03 | 2.4221: Install compressor air intakes in coolest locations | $1,185 | $400 |
$904
21,109
kWh
|
$281
-
kW-mo/yr
|
- | - | - | - | |
04 | 2.7122: Disconnect ballasts | $1,021 | $1,040 |
$677
15,818
kWh
|
$283
-
kW-mo/yr
|
- | - | - | $61 | |
05 | 2.4239: Eliminate or reduce compressed air usage | $995 | $175 |
$861
20,115
kWh
|
$134
-
kW-mo/yr
|
- | - | - | - | |
06 | 2.7135: Install occupancy sensors | $599 | $1,050 |
$381
8,898
kWh
|
$218
-
kW-mo/yr
|
- | - | - | - | |
07 | 2.4231: Reduce the pressure of compressed air to the minimum required | $559 | - |
$394
9,215
kWh
|
$165
-
kW-mo/yr
|
- | - | - | - | |
08 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $524 | $800 |
$403
9,405
kWh
|
$121
-
kW-mo/yr
|
- | - | - | - | |
09 | 2.2136: Install / repair insulation on steam lines | $182 | $405 | - | - |
$182
-
MMBtu
|
- | - | - | |
10 | 3.4154: Eliminate leaks in water lines and valves | $5,689 | $750 | - | - |
$3,240
-
MMBtu
|
$2,449
-
Tgal
|
- | - | |
11 | 3.4114: Replace city water with recycled water via cooling tower | $4,828 | $12,000 | - | - | - |
$4,828
-
Tgal
|
- | - | |
12 | 3.5316: Contract a wood pallet recycling company | $10,000 | $250 | - | - | - | - | $10,000 | - | |
13 | 4.652: Replace existing equipment with more suitable substitutes | $2,250 | $400 | - | - | - | - | - | $2,250 | |
TOTAL RECOMMENDED | $40,025 | $31,430 |
$12,788
298,787
kWh
|
$4,227
-
kW-mo/yr
|
$3,422
-
MMBtu
|
$7,277
-
Tgal
|
$10,000 | $2,311 | ||
TOTAL IMPLEMENTED | $12,419 | $7,015 |
$3,242
75,766
kWh
|
$1,056
-
kW-mo/yr
|
$3,422
-
MMBtu
|
$2,449
-
Tgal
|
- | $2,250 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs