Assessment Year | 2001 |
---|---|
Principal Product | Printed Circuit Boards |
NAICS |
n/a
|
SIC | 3672: Printed Circuit Boards |
Sales Range | $10 M to 50M |
# of Employees | 106 |
Plant Area |
67,000
ft2
|
Annual Production | 40,000
pieces
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Illinois |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $281,246 | 6,725,616 |
kWh
|
$0.042 |
Electricity Demand | $151,545 | 12,397 |
kW-mo/yr
|
$12.22 |
Electricity Fees | $480 | - |
|
- |
Natural Gas | $86,532 | 23,705 |
MMBtu
|
$3.65 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $55,329 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Administrative Changes Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $12,426 | $17,500 | n/a |
$12,880
463,320
kWh
|
$6,553
-
kW-mo/yr
|
$(-7,007.0)
-
MMBtu
|
- | - | - |
02 | 2.1123: Install automatic stack damper | $5,898 | $8,000 | n/a | - | - |
$5,898
-
MMBtu
|
- | - | - |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,193 | $600 |
$1,189
42,733
kWh
|
$1,004
-
kW-mo/yr
|
- | - | - | - | |
04 | 2.4221: Install compressor air intakes in coolest locations | $1,608 | $1,000 |
$984
35,373
kWh
|
$624
-
kW-mo/yr
|
- | - | - | - | |
05 | 2.4133: Use most efficient type of electric motors | $1,047 | $2,060 |
$641
23,072
kWh
|
$406
-
kW-mo/yr
|
- | - | - | - | |
06 | 2.7135: Install occupancy sensors | $908 | $675 |
$333
12,025
kWh
|
$575
-
kW-mo/yr
|
- | - | - | - | |
07 | 2.1222: Install turbulators | $599 | $1,700 | - | - |
$599
-
MMBtu
|
- | - | - | |
08 | 3.4113: Treat and reuse rinse waters | $25,872 | $12,000 | n/a | - | - | - |
$25,872
-
Tgal
|
- | - |
09 | 4.521: Clear and rent existing space | $4,700 | $2,500 | - | - | - | - | $4,700 | - | |
10 | 4.821: Pay bills on time to avoid late fees | $78 | - | - | - | - | - | - | $78 | |
TOTAL RECOMMENDED | $55,329 | $46,035 |
$16,027
576,523
kWh
|
$9,162
-
kW-mo/yr
|
$(-510.0)
-
MMBtu
|
$25,872
-
Tgal
|
$4,700 | $78 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Administrative Changes Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs