Assessment Year | 2001 |
---|---|
Principal Product | Aluminum and Zinc Die Castings |
NAICS |
n/a
|
SIC | 3363: Aluminum Die-Castings |
Sales Range | $10 M to 50M |
# of Employees | 150 |
Plant Area |
82,200
ft2
|
Annual Production | 8,000,000
lb
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Illinois |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $341,934 | 9,122,802 |
kWh
|
$0.037 |
Electricity Demand | $276,339 | 19,707 |
kW-mo/yr
|
$14.02 |
Electricity Fees | $6,444 | - |
|
- |
Natural Gas | $44,986 | 13,576 |
MMBtu
|
$3.31 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $39,343 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $28,605 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | One-time Revenue or Avoided Cost Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $6,764 | $9,860 | n/a |
$4,383
116,940
kWh
|
$2,381
-
kW-mo/yr
|
- | - | - | - |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $4,182 | - |
$2,437
65,064
kWh
|
$1,745
-
kW-mo/yr
|
- | - | - | - | |
03 | 2.7135: Install occupancy sensors | $2,842 | $1,800 |
$1,155
30,774
kWh
|
$1,687
-
kW-mo/yr
|
- | - | - | - | |
04 | 2.4221: Install compressor air intakes in coolest locations | $2,230 | $1,000 |
$1,299
34,584
kWh
|
$931
-
kW-mo/yr
|
- | - | - | - | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,341 | $400 |
$781
20,809
kWh
|
$560
-
kW-mo/yr
|
- | - | - | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $526 | $488 |
$193
5,275
kWh
|
$333
-
kW-mo/yr
|
- | - | - | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $130 | $172 |
$50
1,465
kWh
|
$25
-
kW-mo/yr
|
- | - | $55 | - | |
08 | 3.3131: Use evaporation to concentrate material | $20,240 | $3,600 | - | - |
$20,240
-
Tgal
|
- | - | - | |
09 | 3.5217: Reuse / recycle/ sell paper products | $551 | $200 | - | - | - |
$551
-
lb
|
- | - | |
10 | 4.821: Pay bills on time to avoid late fees | $537 | - | - | - | - | - | - | $537 | |
TOTAL RECOMMENDED | $39,343 | $17,520 |
$10,298
274,911
kWh
|
$7,662
-
kW-mo/yr
|
$20,240
-
Tgal
|
$551
-
lb
|
$55 | $537 | ||
TOTAL IMPLEMENTED | $28,605 | $5,800 |
$4,373
116,647
kWh
|
$3,992
-
kW-mo/yr
|
$20,240
-
Tgal
|
- | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | One-time Revenue or Avoided Cost Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs