| Assessment Year | 2001 |
|---|---|
| Principal Product | Components for Gas Ranges |
| NAICS |
n/a
|
| SIC | 3494: Valves and Pipe Fittings, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 450 |
| Plant Area |
200,000
ft2
|
| Annual Production | 31,000,000
units
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | Illinois |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $579,125 | 10,462,486 |
kWh
|
$0.055 |
| Electricity Demand | $17,315 | 24,018 |
kW-mo/yr
|
$0.72 |
| Electricity Fees | $1,273 | - |
|
- |
| Natural Gas | $129,524 | 38,433 |
MMBtu
|
$3.37 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $59,152 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $7,853 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4133: Use most efficient type of electric motors | $9,662 | $12,500 |
$9,485
171,161
kWh
|
$177
-
kW-mo/yr
|
- | - | - | |
| 02 | 2.7135: Install occupancy sensors | $8,517 | $5,700 |
$8,079
145,955
kWh
|
$438
-
kW-mo/yr
|
- | - | - | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $7,853 | $1,300 |
$7,661
138,335
kWh
|
$192
-
kW-mo/yr
|
- | - | - | |
| 04 | 2.4221: Install compressor air intakes in coolest locations | $3,269 | $600 |
$3,189
57,444
kWh
|
$80
-
kW-mo/yr
|
- | - | - | |
| 05 | 3.3131: Use evaporation to concentrate material | $12,394 | $15,000 | - | - |
$12,394
-
Tgal
|
- | - | |
| 06 | 3.4151: Minimize water usage | $524 | $575 | - | - |
$524
-
Tgal
|
- | - | |
| 07 | 4.421: Modify current incentive program | $15,600 | $10,000 | - | - | - | $15,600 | - | |
| 08 | 2.8112: Combine utility meters | $1,333 | $1,500 | - | - | - | - | $1,333 | |
| TOTAL RECOMMENDED | $59,152 | $47,175 |
$28,414
512,895
kWh
|
$887
-
kW-mo/yr
|
$12,918
-
Tgal
|
$15,600 | $1,333 | ||
| TOTAL IMPLEMENTED | $7,853 | $1,300 |
$7,661
138,335
kWh
|
$192
-
kW-mo/yr
|
- | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs