ITAC Assessment: BD0176
ITAC logo
ITAC Assessment: BD0176
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2001
Principal Product Components for Gas Ranges
NAICS
n/a
SIC 3494: Valves and Pipe Fittings, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 450
Plant Area 200,000
ft2
Annual Production 31,000,000
units
Production Hrs. Annual 6,240
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $579,125 10,462,486
kWh
Electricity Demand $17,315 24,018
kW-mo/yr
Electricity Fees $1,273 -
Natural Gas $129,524 38,433
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $59,152 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $7,853

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Water Disposal Savings Personnel Changes Savings One-time Revenue or Avoided Cost Savings
01 2.4133: Use most efficient type of electric motors $9,662 $12,500 $9,485
171,161
kWh
$177
-
kW-mo/yr
- - -
02 2.7135: Install occupancy sensors $8,517 $5,700 $8,079
145,955
kWh
$438
-
kW-mo/yr
- - -
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $7,853 $1,300 $7,661
138,335
kWh
$192
-
kW-mo/yr
- - -
04 2.4221: Install compressor air intakes in coolest locations $3,269 $600 $3,189
57,444
kWh
$80
-
kW-mo/yr
- - -
05 3.3131: Use evaporation to concentrate material $12,394 $15,000 - - $12,394
-
Tgal
- -
06 3.4151: Minimize water usage $524 $575 - - $524
-
Tgal
- -
07 4.421: Modify current incentive program $15,600 $10,000 - - - $15,600 -
08 2.8112: Combine utility meters $1,333 $1,500 - - - - $1,333
TOTAL RECOMMENDED $59,152 $47,175 $28,414
512,895
kWh
$887
-
kW-mo/yr
$12,918
-
Tgal
$15,600 $1,333
TOTAL IMPLEMENTED $7,853 $1,300 $7,661
138,335
kWh
$192
-
kW-mo/yr
- - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Water Disposal Savings Personnel Changes Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs