ITAC Assessment: KU0321
ITAC logo
ITAC Assessment: KU0321
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1990
Principal Product METAL CONTAINERS
NAICS
n/a
SIC 3412: Metal Shipping Barrels, Drums, Kegs, and Pails
Sales Range $10
M
to 50
M
# of Employees 300
Plant Area
n/a
Annual Production 15,000
pieces
Production Hrs. Annual 4,165
hrs
Location (State) Nebraska

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $152,142 3,259,965
kWh
Natural Gas $77,791 20,672
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $32,489 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $30,313

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.8113: Purchase gas directly from a contract gas supplier $17,845 $10,000 - $17,845
-
MMBtu
-
02 3.4115: Recover and reuse cooling water $8,554 $10,000 - - $8,554
03 2.1233: Analyze flue gas for proper air/fuel ratio $1,810 - - $2,610
-
MMBtu
$(-800.0)
04 2.1222: Install turbulators $1,981 $1,000 - $1,981
-
MMBtu
-
05 2.7142: Utilize higher efficiency lamps and/or ballasts $601 $2,322 $601
12,896
kWh
- -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $123 $127 $123
2,638
kWh
- -
07 2.3131: Reschedule plant operations or reduce load to avoid peaks $1,575 $200 $1,575
-
kWh
- -
TOTAL RECOMMENDED $32,489 $23,649 $2,299
15,534
kWh
$22,436
-
MMBtu
$7,754
TOTAL IMPLEMENTED $30,313 $21,127 $123
2,638
kWh
$22,436
-
MMBtu
$7,754
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs