| Assessment Year | 1990 |
|---|---|
| Principal Product | METAL CONTAINERS |
| NAICS |
n/a
|
| SIC | 3412: Metal Shipping Barrels, Drums, Kegs, and Pails |
| Sales Range | $10 M to 50M |
| # of Employees | 300 |
| Plant Area |
n/a
|
| Annual Production | 15,000
pieces
|
| Production Hrs. Annual | 4,165
hrs
|
| Location (State) | Nebraska |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $152,142 | 3,259,965 |
kWh
|
$0.047 |
| Natural Gas | $77,791 | 20,672 |
MMBtu
|
$3.76 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $32,489 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $30,313 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.8113: Purchase gas directly from a contract gas supplier | $17,845 | $10,000 | - |
$17,845
-
MMBtu
|
- | |
| 02 | 3.4115: Recover and reuse cooling water | $8,554 | $10,000 | - | - | $8,554 | |
| 03 | 2.1233: Analyze flue gas for proper air/fuel ratio | $1,810 | - | - |
$2,610
-
MMBtu
|
$(-800.0) | |
| 04 | 2.1222: Install turbulators | $1,981 | $1,000 | - |
$1,981
-
MMBtu
|
- | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $601 | $2,322 |
$601
12,896
kWh
|
- | - | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $123 | $127 |
$123
2,638
kWh
|
- | - | |
| 07 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $1,575 | $200 |
$1,575
-
kWh
|
- | - | |
| TOTAL RECOMMENDED | $32,489 | $23,649 |
$2,299
15,534
kWh
|
$22,436
-
MMBtu
|
$7,754 | ||
| TOTAL IMPLEMENTED | $30,313 | $21,127 |
$123
2,638
kWh
|
$22,436
-
MMBtu
|
$7,754 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs