ITAC Assessment: BD0152
ITAC logo
ITAC Assessment: BD0152
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product Soft Gaskets
NAICS
n/a
SIC 3053: Gaskets, Packing, and Sealing Devices
Sales Range $50
M
to 100
M
# of Employees 300
Plant Area 175,000
ft2
Annual Production 2,000,000
lb
Production Hrs. Annual 6,240
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $126,423 3,876,612
kWh
Electricity Demand $100,090 8,679
kW-mo/yr
Electricity Fees $4,163 -
Natural Gas $77,010 20,960
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $324,128 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $24,615

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Other Liquid (non-haz) Savings Solid Waste (non-haz) Savings Administrative Changes Savings Ancillary Material Cost Savings Primary Product Savings Increase in Production Savings
01 2.4133: Use most efficient type of electric motors $2,650 $1,000 $1,575
48,359
kWh
$1,075
-
kW-mo/yr
- - - - - -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $2,145 $3,010 $1,417
43,669
kWh
$728
-
kW-mo/yr
- - - - - -
03 2.4221: Install compressor air intakes in coolest locations $1,125 $1,050 $418
12,896
kWh
$707
-
kW-mo/yr
- - - - - -
04 2.7135: Install occupancy sensors $745 $700 $493
15,240
kWh
$252
-
kW-mo/yr
- - - - - -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $180 $235 $56
1,758
kWh
$28
-
kW-mo/yr
- - - $56 $40 -
06 3.5315: Lease / purchase baler; sell cardboard to recycler $295,145 $8,000 - - - $295,145
-
lb
- - - -
07 3.5315: Lease / purchase baler; sell cardboard to recycler $17,779 $2,000 - - $17,779
-
gal
- - - - -
08 4.421: Modify current incentive program $4,186 $8,000 - - - - - - - $4,186
09 4.821: Pay bills on time to avoid late fees $173 - - - - - $173 - - -
TOTAL RECOMMENDED $324,128 $23,995 $3,959
121,922
kWh
$2,790
-
kW-mo/yr
$17,779
-
gal
$295,145
-
lb
$173 $56 $40 $4,186
TOTAL IMPLEMENTED $24,615 $11,000 $1,575
48,359
kWh
$1,075
-
kW-mo/yr
$17,779
-
gal
- - - - $4,186
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Other Liquid (non-haz) Savings Solid Waste (non-haz) Savings Administrative Changes Savings Ancillary Material Cost Savings Primary Product Savings Increase in Production Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs