ITAC Assessment: BD0128
ITAC logo
ITAC Assessment: BD0128
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Sand Castings
NAICS
n/a
SIC 3339: Primary Smelting and Refining of Nonferrous Metals, Except Copper and Aluminum
Sales Range $5
M
to 10
M
# of Employees 98
Plant Area 50,000
ft2
Annual Production 2,500,000
lb
Production Hrs. Annual 6,240
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $187,297 5,951,934
kWh
Electricity Demand $64,759 6,264
kW-mo/yr
Electricity Fees $312 -
Natural Gas $46,847 9,800
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $59,795 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Water Disposal Savings Solid Waste (non-haz) Savings One-time Revenue or Avoided Cost Savings
01 2.2437: Recover waste heat from equipment $16,490 $25,000 $6,128
192,849
kWh
$10,362
-
MMBtu
- - -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $4,012 $600 $4,012
127,491
kWh
- - - -
03 2.4231: Reduce the pressure of compressed air to the minimum required $2,032 - $2,032
64,478
kWh
- - - -
04 2.4221: Install compressor air intakes in coolest locations $1,539 $500 $1,539
48,945
kWh
- - - -
05 2.4314: Use synthetic lubricant $1,524 $600 $1,524
48,359
kWh
- - - -
06 2.7135: Install occupancy sensors $1,231 $750 $1,231
38,980
kWh
- - - -
07 3.5315: Lease / purchase baler; sell cardboard to recycler $11,183 $8,000 - - - $11,183
-
lb
-
08 3.4151: Minimize water usage $996 $1,705 - - $996
-
Tgal
- -
09 2.8114: Change rate schedules or other changes in utility service $12,988 $500 - - - - $12,988
10 3.6192: Use a less expensive method of waste removal $7,800 $500 - - - - $7,800
TOTAL RECOMMENDED $59,795 $38,155 $16,466
521,102
kWh
$10,362
-
MMBtu
$996
-
Tgal
$11,183
-
lb
$20,788
TOTAL IMPLEMENTED - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Water Disposal Savings Solid Waste (non-haz) Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs