Assessment Year | 1998 |
---|---|
Principal Product | Turbine Pumps |
NAICS |
n/a
|
SIC | 3561: Pumps and Pumping Equipment |
Sales Range | $1 M to 5M |
# of Employees | 62 |
Plant Area |
93,517
ft2
|
Annual Production | 1,275
pieces
|
Production Hrs. Annual | 2,210
hrs
|
Location (State) | Illinois |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $51,799 | 1,257,034 |
kWh
|
$0.041 |
Electricity Demand | $29,013 | 3,994 |
kW-mo/yr
|
$7.26 |
Electricity Fees | $3,200 | - |
|
- |
Natural Gas | $39,363 | 7,685 |
MMBtu
|
$5.12 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $31,782 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $17,800 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $9,281 | $15,250 |
$5,307
126,905
kWh
|
$3,545
-
kW-mo/yr
|
- | - | $429 | |
02 | 2.7135: Install occupancy sensors | $5,471 | $2,025 |
$3,502
83,822
kWh
|
$1,969
-
kW-mo/yr
|
- | - | - | |
03 | 2.1213: Direct warmest air to combustion intake | $2,053 | $5,000 | - | - |
$2,053
-
MMBtu
|
- | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,083 | $2,257 |
$649
15,533
kWh
|
$434
-
kW-mo/yr
|
- | - | - | |
05 | 2.4221: Install compressor air intakes in coolest locations | $281 | $200 |
$168
4,103
kWh
|
$113
-
kW-mo/yr
|
- | - | - | |
06 | 3.5111: Filter and reuse hydraulic oil | $4,256 | $1,125 | - | - | - | - | $4,256 | |
07 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $2,147 | $250 | - | - | - | - | $2,147 | |
08 | 3.2123: Convert to high volume low pressure (hvlp) paint guns | $1,921 | $1,300 | - | - | - |
$1,921
-
gal
|
- | |
09 | 4.112: Replace old machine with new automatic multi-station tool | $5,289 | $4,395 | - | - | - | - | $5,289 | |
TOTAL RECOMMENDED | $31,782 | $31,802 |
$9,626
230,363
kWh
|
$6,061
-
kW-mo/yr
|
$2,053
-
MMBtu
|
$1,921
-
gal
|
$12,121 | ||
TOTAL IMPLEMENTED | $17,800 | $22,152 |
$5,956
142,438
kWh
|
$3,979
-
kW-mo/yr
|
- | - | $7,865 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs