| Assessment Year | 1998 |
|---|---|
| Principal Product | Machined Parts |
| NAICS |
n/a
|
| SIC | 3728: Aircraft Parts and Auxiliary Equipment, Not Elsewhere Classified |
| Sales Range | $5 M to 10M |
| # of Employees | 62 |
| Plant Area |
68,200
ft2
|
| Annual Production | 13,000
pieces
|
| Production Hrs. Annual | 5,512
hrs
|
| Location (State) | Illinois |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $55,908 | 1,366,647 |
kWh
|
$0.041 |
| Electricity Demand | $36,221 | 4,181 |
kW-mo/yr
|
$8.66 |
| Electricity Fees | $192 | - |
|
- |
| Natural Gas | $8,950 | 1,619 |
MMBtu
|
$5.53 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $16,254 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $10,285 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4133: Use most efficient type of electric motors | $5,380 | $13,620 |
$3,813
104,338
kWh
|
$1,567
-
kW-mo/yr
|
- | |
| 02 | 2.4226: Use / purchase optimum sized compressor | $3,513 | $3,513 |
$2,319
62,427
kWh
|
$1,194
-
kW-mo/yr
|
- | |
| 03 | 2.4221: Install compressor air intakes in coolest locations | $733 | $375 |
$484
13,189
kWh
|
$249
-
kW-mo/yr
|
- | |
| 04 | 2.7135: Install occupancy sensors | $729 | $730 |
$484
13,189
kWh
|
$245
-
kW-mo/yr
|
- | |
| 05 | 2.4314: Use synthetic lubricant | $396 | $200 |
$261
7,034
kWh
|
$135
-
kW-mo/yr
|
- | |
| 06 | 3.5311: Recover and reuse waste material | $3,627 | $8,000 | - | - | $3,627 | |
| 07 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $1,613 | - | - | - | $1,613 | |
| 08 | 4.821: Pay bills on time to avoid late fees | $263 | - | - | - | $263 | |
| TOTAL RECOMMENDED | $16,254 | $26,438 |
$7,361
200,177
kWh
|
$3,390
-
kW-mo/yr
|
$5,503 | ||
| TOTAL IMPLEMENTED | $10,285 | $17,708 |
$6,877
186,988
kWh
|
$3,145
-
kW-mo/yr
|
$263 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs