ITAC Assessment: BD0096
ITAC logo
ITAC Assessment: BD0096
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Commercial Business Forms
NAICS
n/a
SIC 2752: Commercial Printing, Lithographic
Sales Range $10
M
to 50
M
# of Employees 140
Plant Area 132,400
ft2
Annual Production 20,000,000
lb
Production Hrs. Annual 6,240
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $107,876 3,110,492
kWh
Electricity Demand $62,530 7,940
kW-mo/yr
Electricity Fees $296 -
Natural Gas $19,590 3,413
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $21,398 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,898

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Administrative Changes Savings
01 2.2437: Recover waste heat from equipment $4,125 $1,500 - - $4,125
-
MMBtu
- -
02 2.4133: Use most efficient type of electric motors $3,867 $12,220 $2,291
65,944
kWh
$1,576
-
kW-mo/yr
- - -
03 2.7135: Install occupancy sensors $2,223 $400 $1,521
43,962
kWh
$702
-
kW-mo/yr
- - -
04 2.4221: Install compressor air intakes in coolest locations $1,597 $800 $1,112
31,946
kWh
$485
-
kW-mo/yr
- - -
05 2.2437: Recover waste heat from equipment $1,363 $3,500 - - $1,363
-
MMBtu
- -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $1,177 $2,086 $787
22,567
kWh
$390
-
kW-mo/yr
- - -
07 3.5315: Lease / purchase baler; sell cardboard to recycler $301 $400 - - - $585
-
lb
$(-284.0)
08 3.5316: Contract a wood pallet recycling company $300 $300 - - - - $300
09 4.322: Eliminate old stock and modify inventory control $6,445 $8,600 - - - - $6,445
TOTAL RECOMMENDED $21,398 $29,806 $5,711
164,419
kWh
$3,153
-
kW-mo/yr
$5,488
-
MMBtu
$585
-
lb
$6,461
TOTAL IMPLEMENTED $1,898 $1,200 $1,112
31,946
kWh
$485
-
kW-mo/yr
- $585
-
lb
$(-284.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs