Assessment Year | 1997 |
---|---|
Principal Product | Commercial Business Forms |
NAICS |
n/a
|
SIC | 2752: Commercial Printing, Lithographic |
Sales Range | $10 M to 50M |
# of Employees | 140 |
Plant Area |
132,400
ft2
|
Annual Production | 20,000,000
lb
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Illinois |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $107,876 | 3,110,492 |
kWh
|
$0.035 |
Electricity Demand | $62,530 | 7,940 |
kW-mo/yr
|
$7.88 |
Electricity Fees | $296 | - |
|
- |
Natural Gas | $19,590 | 3,413 |
MMBtu
|
$5.74 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $21,398 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $1,898 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.2437: Recover waste heat from equipment | $4,125 | $1,500 | - | - |
$4,125
-
MMBtu
|
- | - | |
02 | 2.4133: Use most efficient type of electric motors | $3,867 | $12,220 |
$2,291
65,944
kWh
|
$1,576
-
kW-mo/yr
|
- | - | - | |
03 | 2.7135: Install occupancy sensors | $2,223 | $400 |
$1,521
43,962
kWh
|
$702
-
kW-mo/yr
|
- | - | - | |
04 | 2.4221: Install compressor air intakes in coolest locations | $1,597 | $800 |
$1,112
31,946
kWh
|
$485
-
kW-mo/yr
|
- | - | - | |
05 | 2.2437: Recover waste heat from equipment | $1,363 | $3,500 | - | - |
$1,363
-
MMBtu
|
- | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,177 | $2,086 |
$787
22,567
kWh
|
$390
-
kW-mo/yr
|
- | - | - | |
07 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $301 | $400 | - | - | - |
$585
-
lb
|
$(-284.0) | |
08 | 3.5316: Contract a wood pallet recycling company | $300 | $300 | - | - | - | - | $300 | |
09 | 4.322: Eliminate old stock and modify inventory control | $6,445 | $8,600 | - | - | - | - | $6,445 | |
TOTAL RECOMMENDED | $21,398 | $29,806 |
$5,711
164,419
kWh
|
$3,153
-
kW-mo/yr
|
$5,488
-
MMBtu
|
$585
-
lb
|
$6,461 | ||
TOTAL IMPLEMENTED | $1,898 | $1,200 |
$1,112
31,946
kWh
|
$485
-
kW-mo/yr
|
- |
$585
-
lb
|
$(-284.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs