Assessment Year | 1997 |
---|---|
Principal Product | Injection Moldings |
NAICS |
n/a
|
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 140 |
Plant Area |
41,000
ft2
|
Annual Production | 450,000
lb
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Illinois |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $129,641 | 2,779,895 |
kWh
|
$0.047 |
Electricity Demand | $81,024 | 6,250 |
kW-mo/yr
|
$12.96 |
Electricity Fees | $1,803 | - |
|
- |
Natural Gas | $6,043 | 1,376 |
MMBtu
|
$4.39 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $102,927 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $62,095 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $38,324 | $24,791 |
$31,281
671,161
kWh
|
$18,589
-
kW-mo/yr
|
$(-11,546.0)
-
MMBtu
|
- | - | - | - | - | |
02 | 2.8114: Change rate schedules or other changes in utility service | $37,336 | $500 | - | - | - | - | - | $37,336 | - | - | |
03 | 2.4133: Use most efficient type of electric motors | $7,396 | $8,110 |
$4,618
99,062
kWh
|
$2,778
-
kW-mo/yr
|
- | - | - | - | - | - | |
04 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $3,496 | $1,920 |
$3,553
76,202
kWh
|
$1,218
-
kW-mo/yr
|
$(-1,275.0)
-
MMBtu
|
- | - | - | - | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,875 | $2,077 |
$1,218
26,084
kWh
|
$657
-
kW-mo/yr
|
- | - | - | - | - | - | |
06 | 2.4221: Install compressor air intakes in coolest locations | $1,261 | $400 |
$966
20,809
kWh
|
$295
-
kW-mo/yr
|
- | - | - | - | - | - | |
07 | 2.7135: Install occupancy sensors | $783 | $600 |
$499
10,844
kWh
|
$284
-
kW-mo/yr
|
- | - | - | - | - | - | |
08 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $9,643 | $7,500 | - | - | - |
$3,473
-
lb
|
$(-660.0) | - | - | $6,830 | |
09 | 3.5311: Recover and reuse waste material | $2,813 | $2,250 |
$(-750.0)
(-16,120)
kWh
|
- | - |
$132
-
lb
|
$(-3,900.0) | - | $7,331 | - | |
TOTAL RECOMMENDED | $102,927 | $48,148 |
$41,385
888,042
kWh
|
$23,821
-
kW-mo/yr
|
$(-12,821.0)
-
MMBtu
|
$3,605
-
lb
|
$(-4,560.0) | $37,336 | $7,331 | $6,830 | ||
TOTAL IMPLEMENTED | $62,095 | $45,728 |
$37,832
811,840
kWh
|
$22,603
-
kW-mo/yr
|
$(-11,546.0)
-
MMBtu
|
$3,605
-
lb
|
$(-4,560.0) | - | $7,331 | $6,830 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs