Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product Paper Products
NAICS
n/a
SIC 2671: Packaging Paper and Plastics Film, Coated and Laminated
Sales Range $10
M
to 50
M
# of Employees 89
Plant Area 98,940
ft2
Annual Production 2,160,000,000
thousand feet
Production Hrs. Annual 7,488
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $120,662 3,892,732
kWh
Electricity Demand $88,928 6,973
kW-mo/yr
Electricity Fees $2,852 -
Natural Gas $146,661 39,887
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $27,964 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $13,965

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings Ancillary Material Cost Savings Water Consumption Savings
01 2.4133: Use most efficient type of electric motors $7,122 $12,270 $4,754
153,283
kWh
$2,368
-
kW-mo/yr
- - -
02 2.4221: Install compressor air intakes in coolest locations $2,590 $800 $1,548
49,824
kWh
$1,042
-
kW-mo/yr
- - -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $1,611 $2,563 $856
27,550
kWh
$755
-
kW-mo/yr
- - -
04 2.7135: Install occupancy sensors $1,441 $1,500 $551
17,878
kWh
$890
-
kW-mo/yr
- - -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $1,531 $2,590 $773
24,912
kWh
$510
-
kW-mo/yr
$34 $214 -
06 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,111 $1,020 $742
24,033
kWh
$369
-
kW-mo/yr
- - -
07 2.7243: Improve air circulation with destratification fans / other methods $562 $660 - $562
-
kW-mo/yr
- - -
08 3.3122: Use filtration, centrifuging to remove contaminants $11,996 $9,045 $(-350.0)
(-11,430)
kWh
- $1,680 - $10,666
-
Tgal
TOTAL RECOMMENDED $27,964 $30,448 $8,874
286,050
kWh
$6,496
-
kW-mo/yr
$1,714 $214 $10,666
-
Tgal
TOTAL IMPLEMENTED $13,965 $19,243 $8,673
279,602
kWh
$5,044
-
kW-mo/yr
$34 $214 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings Ancillary Material Cost Savings Water Consumption Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs