| Assessment Year | 1996 |
|---|---|
| Principal Product | Sewer Cleaners |
| NAICS |
n/a
|
| SIC | 3589: Service Industry Machinery, Not Elsewhere Classified |
| Sales Range | $50 M to 100M |
| # of Employees | 300 |
| Plant Area |
240,000
ft2
|
| Annual Production | 342
pieces
|
| Production Hrs. Annual | 7,488
hrs
|
| Location (State) | Illinois |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $120,749 | 3,031,653 |
kWh
|
$0.040 |
| Electricity Demand | $87,817 | 7,199 |
kW-mo/yr
|
$12.20 |
| Electricity Fees | $13,621 | - |
|
- |
| Natural Gas | $79,526 | 24,549 |
MMBtu
|
$3.24 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $222,486 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $210,717 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Other Liquid (haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Water Consumption Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7135: Install occupancy sensors | $9,949 | $3,500 |
$6,653
167,057
kWh
|
$3,296
-
kW-mo/yr
|
- | - | - | - | - | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,990 | $17,287 |
$2,990
75,029
kWh
|
$3,000
-
kW-mo/yr
|
- | - | - | - | - | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,318 | $1,200 |
$3,318
83,236
kWh
|
- | - | - | - | - | - | |
| 04 | 2.4133: Use most efficient type of electric motors | $1,948 | $3,740 |
$1,424
35,756
kWh
|
$524
-
kW-mo/yr
|
- | - | - | - | - | |
| 05 | 2.4221: Install compressor air intakes in coolest locations | $1,874 | $750 |
$1,874
47,186
kWh
|
- | - | - | - | - | - | |
| 06 | 3.2123: Convert to high volume low pressure (hvlp) paint guns | $171,645 | $4,370 | - | - | - | - | - | $171,645 | - | |
| 07 | 3.3125: Use distillation, evaporation to remove contaminants | $23,857 | $18,500 |
$(-369.0)
(-9,379)
kWh
|
- | - |
$10,786
-
gal
|
$(-5,018.0) | $18,458 | - | |
| 08 | 3.5311: Recover and reuse waste material | $3,905 | $1,000 |
$(-32.0)
(-2,345)
kWh
|
$(-99.0)
-
kW-mo/yr
|
$2,831
-
Tgal
|
- | - | - |
$1,205
-
Tgal
|
|
| TOTAL RECOMMENDED | $222,486 | $50,347 |
$15,858
396,540
kWh
|
$6,721
-
kW-mo/yr
|
$2,831
-
Tgal
|
$10,786
-
gal
|
$(-5,018.0) | $190,103 |
$1,205
-
Tgal
|
||
| TOTAL IMPLEMENTED | $210,717 | $31,310 |
$11,026
276,670
kWh
|
$3,820
-
kW-mo/yr
|
- |
$10,786
-
gal
|
$(-5,018.0) | $190,103 | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Other Liquid (haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Water Consumption Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs