ITAC Assessment: BD0057
ITAC logo
ITAC Assessment: BD0057
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product Garage Door Springs and Tracks
NAICS
n/a
SIC 3442: Metal Doors, Sash, Frames, Molding, and Trim Manufacturing
Sales Range $10
M
to 50
M
# of Employees 190
Plant Area 274,000
ft2
Annual Production 184,000
pieces
Production Hrs. Annual 6,240
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $59,333 1,747,069
kWh
Electricity Demand $32,192 4,526
kW-mo/yr
Electricity Fees $7,172 -
Natural Gas $41,404 17,083
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $31,629 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $10,361

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Water Disposal Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings Water Consumption Savings
01 2.4226: Use / purchase optimum sized compressor $13,789 $27,000 $2,788
87,339
kWh
$5,636
-
kW-mo/yr
$3,943
-
Tgal
- $1,422 - -
02 2.7135: Install occupancy sensors $5,882 $2,625 $3,029
94,959
kWh
$2,853
-
kW-mo/yr
- - - - -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $4,861 $6,766 $2,562
79,132
kWh
$2,299
-
kW-mo/yr
- - - - -
04 2.4133: Use most efficient type of electric motors $3,689 $6,130 $2,245
70,340
kWh
$1,444
-
kW-mo/yr
- - - - -
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $245 $300 $245
7,620
kWh
- - - - - -
06 3.2123: Convert to high volume low pressure (hvlp) paint guns $1,597 $750 - - - - - $1,597 -
07 3.4115: Recover and reuse cooling water $1,566 $3,018 $(-420.0)
(-6,155)
kWh
- - $(-150.0) - - $2,136
-
Tgal
TOTAL RECOMMENDED $31,629 $46,589 $10,449
333,235
kWh
$12,232
-
kW-mo/yr
$3,943
-
Tgal
$(-150.0) $1,422 $1,597 $2,136
-
Tgal
TOTAL IMPLEMENTED $10,361 $16,214 $4,632
150,937
kWh
$3,743
-
kW-mo/yr
- $(-150.0) - - $2,136
-
Tgal
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Water Disposal Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings Water Consumption Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs