Assessment Year | 1996 |
---|---|
Principal Product | Commercial Rolling Steel Doors |
NAICS |
n/a
|
SIC | 3442: Metal Doors, Sash, Frames, Molding, and Trim Manufacturing |
Sales Range | $5 M to 10M |
# of Employees | 90 |
Plant Area |
80,450
ft2
|
Annual Production | 7,700
pieces
|
Production Hrs. Annual | 4,550
hrs
|
Location (State) | Illinois |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $45,715 | 1,349,062 |
kWh
|
$0.034 |
Electricity Demand | $25,064 | 3,480 |
kW-mo/yr
|
$7.20 |
Electricity Fees | $5,525 | - |
|
- |
Natural Gas | $7,858 | 2,120 |
MMBtu
|
$3.71 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $120,752 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $7,791 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,378 | $8,196 |
$1,544
48,359
kWh
|
$1,834
-
kW-mo/yr
|
- | |
02 | 2.4133: Use most efficient type of electric motors | $3,186 | $7,750 |
$1,695
53,048
kWh
|
$1,491
-
kW-mo/yr
|
- | |
03 | 2.7135: Install occupancy sensors | $1,286 | $900 |
$573
16,999
kWh
|
$713
-
kW-mo/yr
|
- | |
04 | 2.4314: Use synthetic lubricant | $412 | $175 |
$213
6,741
kWh
|
$199
-
kW-mo/yr
|
- | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,010 | $750 |
$1,010
31,360
kWh
|
- | - | |
06 | 2.4221: Install compressor air intakes in coolest locations | $217 | $400 |
$217
6,741
kWh
|
- | - | |
07 | 3.1171: Change product specs | $111,263 | $7,000 | - | - | $111,263 | |
TOTAL RECOMMENDED | $120,752 | $25,171 |
$5,252
163,248
kWh
|
$4,237
-
kW-mo/yr
|
$111,263 | ||
TOTAL IMPLEMENTED | $7,791 | $17,096 |
$4,466
139,508
kWh
|
$3,325
-
kW-mo/yr
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs