Assessment Year | 1996 |
---|---|
Principal Product | Automotive electronics |
NAICS |
n/a
|
SIC | 3679: Electronic Components, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 400 |
Plant Area |
130,000
ft2
|
Annual Production | 25,000,000
pieces
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Illinois |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $207,854 | 5,381,301 |
kWh
|
$0.039 |
Electricity Demand | $115,332 | 10,984 |
kW-mo/yr
|
$10.50 |
Electricity Fees | $14,747 | - |
|
- |
Natural Gas | $7,578 | 1,548 |
MMBtu
|
$4.90 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $33,100 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $11,352 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Solid Waste (non-haz) Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4221: Install compressor air intakes in coolest locations | $5,967 | $1,000 |
$4,904
130,422
kWh
|
$1,063
-
kW-mo/yr
|
- | - | |
02 | 2.7135: Install occupancy sensors | $3,769 | $525 |
$2,681
71,219
kWh
|
$1,088
-
kW-mo/yr
|
- | - | |
03 | 2.4133: Use most efficient type of electric motors | $2,287 | $4,900 |
$1,776
47,186
kWh
|
$511
-
kW-mo/yr
|
- | - | |
04 | 2.4314: Use synthetic lubricant | $2,516 | $240 |
$2,094
55,686
kWh
|
$422
-
kW-mo/yr
|
- | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,554 | $4,416 |
$733
19,637
kWh
|
$821
-
kW-mo/yr
|
- | - | |
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $974 | $525 |
$818
21,688
kWh
|
$156
-
kW-mo/yr
|
- | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $570 | $723 |
$414
11,137
kWh
|
$156
-
kW-mo/yr
|
- | - | |
08 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $10,300 | $25,000 | - | - | - |
$10,300
-
lb
|
|
09 | 3.4151: Minimize water usage | $3,512 | $8,000 | - | - |
$3,512
-
Tgal
|
- | |
10 | 3.5212: Regrind, reuse, or sell scrap plastic parts | $1,651 | $370 | - | - | - |
$1,651
-
lb
|
|
TOTAL RECOMMENDED | $33,100 | $45,699 |
$13,420
356,975
kWh
|
$4,217
-
kW-mo/yr
|
$3,512
-
Tgal
|
$11,951
-
lb
|
||
TOTAL IMPLEMENTED | $11,352 | $11,564 |
$8,645
230,070
kWh
|
$2,707
-
kW-mo/yr
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Solid Waste (non-haz) Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs