Assessment Year | 2006 |
---|---|
Principal Product | Ventilation and Air conditioning duct work |
NAICS | 332322: Sheet Metal Work Manufacturing |
SIC | 3444: Sheet Metal Work |
Sales Range | $5 M to 10M |
# of Employees | 145 |
Plant Area |
110,000
ft2
|
Annual Production | 5,000,000
lb
|
Production Hrs. Annual | 2,927
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $151,646 | 1,512,675 |
kWh
|
$0.10 |
Electricity Demand | $36,407 | 6,113 |
kW-mo/yr
|
$5.96 |
Natural Gas | $19,051 | 1,490 |
MMBtu
|
$12.79 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $16,845 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $16,845 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings |
---|---|---|---|---|---|---|---|
01 | 2.3212: Optimize plant power factor | $14,150 | $25,000 | - | - | $14,150 | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,785 | $385 |
$1,465
15,579
kWh
|
$320
-
kW-mo/yr
|
- | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $480 | - |
$395
4,215
kWh
|
$85
-
kW-mo/yr
|
- | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $370 | $370 |
$345
3,679
kWh
|
$25
-
kW-mo/yr
|
- | |
05 | 2.7124: Make a practice of turning off lights when not needed | $60 | - |
$60
601
kWh
|
- | - | |
TOTAL RECOMMENDED | $16,845 | $25,755 |
$2,265
24,074
kWh
|
$430
-
kW-mo/yr
|
$14,150 | ||
TOTAL IMPLEMENTED | $16,845 | $25,755 |
$2,265
24,074
kWh
|
$430
-
kW-mo/yr
|
$14,150 |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs