ITAC Assessment: BD0039
ITAC logo
ITAC Assessment: BD0039
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1995
Principal Product Automobile Parts
NAICS
n/a
SIC 3714: Motor Vehicle Parts and Accessories
Sales Range $10
M
to 50
M
# of Employees 130
Plant Area 46,000
ft2
Annual Production 1,350,000
pieces
Production Hrs. Annual 6,864
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $211,719 3,518,171
kWh
Natural Gas $1,644 280
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $22,163 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $22,163

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.4133: Use most efficient type of electric motors $11,365 $16,630 $11,365
188,746
kWh
02 2.7228: Avoid introducing hot, humid, or dirty air into hvac system $3,955 $2,000 $3,955
65,651
kWh
03 2.4221: Install compressor air intakes in coolest locations $1,953 $1,000 $1,953
32,532
kWh
04 2.7135: Install occupancy sensors $3,985 $825 $3,985
66,237
kWh
05 2.7142: Utilize higher efficiency lamps and/or ballasts $723 $571 $723
12,016
kWh
06 2.7142: Utilize higher efficiency lamps and/or ballasts $182 $305 $182
2,931
kWh
TOTAL RECOMMENDED $22,163 $21,331 $22,163
368,113
kWh
TOTAL IMPLEMENTED $22,163 $21,331 $22,163
368,113
kWh
Yearly Savings* Imp'd Cost* Electricity Usage Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs