| Assessment Year | 1989 |
|---|---|
| Principal Product | ELECTRO STATIC CLEANERS |
| NAICS |
n/a
|
| SIC | 3444: Sheet Metal Work |
| Sales Range | $10 M to 50M |
| # of Employees | 300 |
| Plant Area |
n/a
|
| Annual Production | 50,000
pieces
|
| Production Hrs. Annual | 4,000
hrs
|
| Location (State) | North Carolina |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $242,906 | 4,026,084 |
kWh
|
$0.060 |
| Natural Gas | $63,566 | 16,387 |
MMBtu
|
$3.88 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $35,935 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $35,226 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $10,117 | $1,131 |
$10,117
167,644
kWh
|
- | |
| 02 | 2.4221: Install compressor air intakes in coolest locations | $6,033 | $6,000 | - |
$6,033
-
MMBtu
|
|
| 03 | 2.7226: Use computer programs to optimize hvac performance | $16,183 | $1,000 |
$16,183
268,171
kWh
|
- | |
| 04 | 2.4221: Install compressor air intakes in coolest locations | $392 | $600 |
$392
6,448
kWh
|
- | |
| 05 | 2.2437: Recover waste heat from equipment | $972 | $600 | - |
$972
-
MMBtu
|
|
| 06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $709 | - |
$709
11,723
kWh
|
- | |
| 07 | 2.4133: Use most efficient type of electric motors | $454 | $257 |
$454
7,620
kWh
|
- | |
| 08 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,075 | - |
$1,075
17,878
kWh
|
- | |
| TOTAL RECOMMENDED | $35,935 | $9,588 |
$28,930
479,484
kWh
|
$7,005
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $35,226 | $9,588 |
$28,221
467,761
kWh
|
$7,005
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs