| Assessment Year | 1988 |
|---|---|
| Principal Product | WOOD PANELS & VENEER |
| NAICS |
n/a
|
| SIC | 2436: Softwood Veneer and Plywood |
| Sales Range | $10 M to 50M |
| # of Employees | 227 |
| Plant Area |
n/a
|
| Annual Production | 11,250
thousand feet
|
| Production Hrs. Annual | 2,000
hrs
|
| Location (State) | North Carolina |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $377,426 | 6,748,828 |
kWh
|
$0.056 |
| Fuel Oil #2 | $29,390 | 4,957 |
MMBtu
|
$5.93 |
| Wood | $160,000 | 172,000 |
MMBtu
|
$0.93 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $35,558 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $32,286 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Fuel Oil #2 Savings | Wood Savings |
|---|---|---|---|---|---|---|---|
| 01 | 3.6123: Burn wood by-products for heat | $22,310 | $2,000 | - |
$29,390
-
MMBtu
|
$(-7,080.0)
-
MMBtu
|
|
| 02 | 2.4133: Use most efficient type of electric motors | $2,302 | $2,745 |
$2,302
41,325
kWh
|
- | - | |
| 03 | 2.4312: Improve lubrication practices | $468 | - |
$468
8,499
kWh
|
- | - | |
| 04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $5,018 | - |
$5,018
89,683
kWh
|
- | - | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,049 | $525 |
$1,049
18,757
kWh
|
- | - | |
| 06 | 2.3191: Use demand controller or load shedder | $3,272 | $3,000 |
$3,272
-
kWh
|
- | - | |
| 07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $597 | $200 |
$597
10,551
kWh
|
- | - | |
| 08 | 2.4221: Install compressor air intakes in coolest locations | $542 | $500 |
$542
9,672
kWh
|
- | - | |
| TOTAL RECOMMENDED | $35,558 | $8,970 |
$13,248
178,487
kWh
|
$29,390
-
MMBtu
|
$(-7,080.0)
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $32,286 | $5,970 |
$9,976
178,487
kWh
|
$29,390
-
MMBtu
|
$(-7,080.0)
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Fuel Oil #2 Savings | Wood Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs