Assessment Year | 1988 |
---|---|
Principal Product | VALVES FOR AUTO INDUSTRY |
NAICS |
n/a
|
SIC | 3714: Motor Vehicle Parts and Accessories |
Sales Range | $10 M to 50M |
# of Employees | 350 |
Plant Area |
n/a
|
Annual Production | 65,000,000
pieces
|
Production Hrs. Annual | 4,800
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $472,326 | 8,228,019 |
kWh
|
$0.057 |
Natural Gas | $137,293 | 32,768 |
MMBtu
|
$4.19 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $64,196 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $61,689 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 3.4115: Recover and reuse cooling water | $47,649 | $18,500 |
$2,133
37,222
kWh
|
- | $45,516 | |
02 | 2.7123: Keep lamps and reflectors clean | $6,328 | $7,000 |
$6,328
110,199
kWh
|
- | - | |
03 | 2.4133: Use most efficient type of electric motors | $1,633 | $1,297 |
$1,633
28,429
kWh
|
- | - | |
04 | 2.4312: Improve lubrication practices | $1,683 | - |
$1,683
29,308
kWh
|
- | - | |
05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $2,501 | - |
$2,501
43,669
kWh
|
- | - | |
06 | 2.2136: Install / repair insulation on steam lines | $367 | $250 | - |
$367
-
MMBtu
|
- | |
07 | 2.2122: Install / repair insulation on condensate lines | $1,050 | $600 | - |
$1,050
-
MMBtu
|
- | |
08 | 2.6214: Shut off pilots in standby equipment | $376 | - | - |
$506
-
MMBtu
|
$(-130.0) | |
09 | 2.4221: Install compressor air intakes in coolest locations | $1,785 | $2,500 |
$1,785
31,067
kWh
|
- | - | |
10 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $824 | $100 |
$824
14,361
kWh
|
- | - | |
TOTAL RECOMMENDED | $64,196 | $30,247 |
$16,887
294,255
kWh
|
$1,923
-
MMBtu
|
$45,386 | ||
TOTAL IMPLEMENTED | $61,689 | $30,147 |
$14,380
250,586
kWh
|
$1,923
-
MMBtu
|
$45,386 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs