Assessment Year | 1987 |
---|---|
Principal Product | CIRCUIT BREAKER CONTACTS |
NAICS |
n/a
|
SIC | 3316: Cold-Rolled Steel Sheet, Strip, and Bars |
Sales Range | $10 M to 50M |
# of Employees | 350 |
Plant Area |
n/a
|
Annual Production | 3,000,000
lb
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $693,847 | 14,223,623 |
kWh
|
$0.049 |
Natural Gas | $124,526 | 24,114 |
MMBtu
|
$5.16 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $22,614 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $2,080 | $1,658 |
$2,080
42,790
kWh
|
- | - | |
02 | 2.4312: Improve lubrication practices | $1,728 | - |
$1,728
35,170
kWh
|
- | - | |
03 | 2.2511: Insulate bare equipment | $8,322 | $900 |
$8,322
170,574
kWh
|
- | - | |
04 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $2,142 | $3,000 |
$3,747
76,788
kWh
|
$(-1,605.0)
-
MMBtu
|
- | |
05 | 2.1233: Analyze flue gas for proper air/fuel ratio | $2,476 | - | - |
$2,976
-
MMBtu
|
$(-500.0) | |
06 | 2.7226: Use computer programs to optimize hvac performance | $2,274 | $3,000 |
$2,274
46,600
kWh
|
- | - | |
07 | 2.7261: Install timers and/or thermostats | $872 | $400 |
$872
17,878
kWh
|
- | - | |
08 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $2,720 | - |
$2,720
55,686
kWh
|
- | - | |
TOTAL RECOMMENDED | $22,614 | $8,958 |
$21,743
445,486
kWh
|
$1,371
-
MMBtu
|
$(-500.0) | ||
TOTAL IMPLEMENTED | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs