ITAC Assessment: AT0074
ITAC logo
ITAC Assessment: AT0074
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1987
Principal Product PLASTIC MOLDINGS
NAICS
n/a
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 275
Plant Area
n/a
Annual Production 25,000,000
lb
Production Hrs. Annual 6,000
hrs
Location (State) North Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $697,762 16,165,006
kWh
Natural Gas $17,905 3,085
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $43,363 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $17,323

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.2614: Use cooling tower or economizer to replace chiller cooling $21,967 $6,000 $21,967
509,086
kWh
- -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $7,236 $18,150 $7,236
167,644
kWh
- -
03 2.2511: Insulate bare equipment $6,123 $5,000 $6,123
141,852
kWh
- -
04 2.7226: Use computer programs to optimize hvac performance $1,341 $1,500 $1,341
31,067
kWh
- -
05 2.4221: Install compressor air intakes in coolest locations $1,132 $3,000 $1,132
26,377
kWh
- -
06 2.2437: Recover waste heat from equipment $2,941 $2,400 - $2,941
-
MMBtu
-
07 2.6214: Shut off pilots in standby equipment $339 - - $389
-
MMBtu
$(-50.0)
08 2.4111: Utilize energy-efficient belts and other improved mechanisms $2,284 - $2,284
53,048
kWh
- -
TOTAL RECOMMENDED $43,363 $36,050 $40,083
929,074
kWh
$3,330
-
MMBtu
$(-50.0)
TOTAL IMPLEMENTED $17,323 $24,650 $16,984
393,611
kWh
$389
-
MMBtu
$(-50.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs