Assessment Year | 1986 |
---|---|
Principal Product | ANALOG DEVICES |
NAICS |
n/a
|
SIC | 3571: Electronic Computers |
Sales Range | $10 M to 50M |
# of Employees | 350 |
Plant Area |
n/a
|
Annual Production | 317,000
pieces
|
Production Hrs. Annual | 4,000
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $516,884 | 11,286,929 |
kWh
|
$0.046 |
Fuel Oil #2 | $32,390 | 9,100 |
MMBtu
|
$3.56 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $27,223 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $2,737 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $966 | $626 |
$966
21,102
kWh
|
- | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $107 | $180 |
$107
2,345
kWh
|
- | |
03 | 2.4221: Install compressor air intakes in coolest locations | $295 | $250 |
$295
6,448
kWh
|
- | |
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $604 | $100 |
$604
13,189
kWh
|
- | |
05 | 2.2437: Recover waste heat from equipment | $1,087 | $2,000 |
$1,087
23,740
kWh
|
- | |
06 | 2.6121: Reduce hot water temperature to the minimum required | $1,033 | - |
$1,033
22,567
kWh
|
- | |
07 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $738 | - |
$738
16,120
kWh
|
- | |
08 | 2.7226: Use computer programs to optimize hvac performance | $6,965 | $1,000 |
$6,965
152,110
kWh
|
- | |
09 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $15,428 | $10,000 |
$23,082
504,103
kWh
|
$(-7,654.0)
-
MMBtu
|
|
TOTAL RECOMMENDED | $27,223 | $14,156 |
$34,877
761,724
kWh
|
$(-7,654.0)
-
MMBtu
|
||
TOTAL IMPLEMENTED | $2,737 | $626 |
$2,737
59,789
kWh
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs