ITAC Assessment: AT0056
ITAC logo
ITAC Assessment: AT0056
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1986
Principal Product ANALOG DEVICES
NAICS
n/a
SIC 3571: Electronic Computers
Sales Range $10
M
to 50
M
# of Employees 350
Plant Area
n/a
Annual Production 317,000
pieces
Production Hrs. Annual 4,000
hrs
Location (State) North Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $516,884 11,286,929
kWh
Fuel Oil #2 $32,390 9,100
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $27,223 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $2,737

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.4133: Use most efficient type of electric motors $966 $626 $966
21,102
kWh
-
02 2.7142: Utilize higher efficiency lamps and/or ballasts $107 $180 $107
2,345
kWh
-
03 2.4221: Install compressor air intakes in coolest locations $295 $250 $295
6,448
kWh
-
04 2.4231: Reduce the pressure of compressed air to the minimum required $604 $100 $604
13,189
kWh
-
05 2.2437: Recover waste heat from equipment $1,087 $2,000 $1,087
23,740
kWh
-
06 2.6121: Reduce hot water temperature to the minimum required $1,033 - $1,033
22,567
kWh
-
07 2.4111: Utilize energy-efficient belts and other improved mechanisms $738 - $738
16,120
kWh
-
08 2.7226: Use computer programs to optimize hvac performance $6,965 $1,000 $6,965
152,110
kWh
-
09 2.1311: Replace electrically-operated equipment with fossil fuel equipment $15,428 $10,000 $23,082
504,103
kWh
$(-7,654.0)
-
MMBtu
TOTAL RECOMMENDED $27,223 $14,156 $34,877
761,724
kWh
$(-7,654.0)
-
MMBtu
TOTAL IMPLEMENTED $2,737 $626 $2,737
59,789
kWh
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs