| Assessment Year | 2008 |
|---|---|
| Principal Product | Snow plows and salt spreaders |
| NAICS | 332999: All Other Miscellaneous Fabricated Metal Product Manufacturing |
| SIC | 3499: Fabricated Metal Products, Not Elsewhere Classified |
| Sales Range | $50 M to 100M |
| # of Employees | 144 |
| Plant Area |
255,000
ft2
|
| Annual Production | 15,500
pieces
|
| Production Hrs. Annual | 5,976
hrs
|
| Location (State) | Michigan |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $195,032 | 4,263,922 |
kWh
|
$0.046 |
| Electricity Demand | $126,411 | 12,348 |
kW-mo/yr
|
$10.24 |
| Natural Gas | $211,966 | 20,770 |
MMBtu
|
$10.21 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $141,872 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $141,872 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $9,453 | $75,348 |
$6,179
134,261
kWh
|
$3,174
-
kW-mo/yr
|
- | - | $100 | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $35,889 | $55,200 |
$23,601
513,059
kWh
|
$12,288
-
kW-mo/yr
|
- | - | - | |
| 03 | 2.7135: Install occupancy sensors | $1,712 | $2,967 |
$987
21,465
kWh
|
$725
-
kW-mo/yr
|
- | - | - | |
| 04 | 2.7122: Disconnect ballasts | $4,311 | $4,750 |
$3,019
65,620
kWh
|
$1,292
-
kW-mo/yr
|
- | - | - | |
| 05 | 2.7133: Use separate switches on perimeter lighting which may be turned off when natural light is available | $395 | $250 |
$273
5,934
kWh
|
$122
-
kW-mo/yr
|
- | - | - | |
| 06 | 2.7124: Make a practice of turning off lights when not needed | $24,605 | - |
$24,560
6,270
kWh
|
$45
-
kW-mo/yr
|
- | - | - | |
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $133 | $398 |
$18
385
kWh
|
$10
-
kW-mo/yr
|
- | $105 | - | |
| 08 | 2.4133: Use most efficient type of electric motors | $1,952 | $15,562 |
$1,266
27,582
kWh
|
$686
-
kW-mo/yr
|
- | - | - | |
| 09 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $200 | $246 |
$129
2,803
kWh
|
$71
-
kW-mo/yr
|
- | - | - | |
| 10 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $13,527 | $30,225 |
$13,527
294,073
kWh
|
- | - | - | - | |
| 11 | 2.4323: Use optimum size and capacity equipment | $6,598 | $9,911 |
$6,598
143,424
kWh
|
- | - | - | - | |
| 12 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $7,138 | $1,380 |
$7,138
155,139
kWh
|
- | - | - | - | |
| 13 | 2.4321: Upgrade obsolete equipment | $17,075 | $5,520 |
$13,085
284,467
kWh
|
$3,990
-
kW-mo/yr
|
- | - | - | |
| 14 | 2.2437: Recover waste heat from equipment | $13,784 | $8,670 | - | - |
$13,784
-
MMBtu
|
- | - | |
| 15 | 2.6241: Reduce temperature of process equipment when on standby | $5,100 | - | - | - |
$5,100
-
MMBtu
|
- | - | |
| TOTAL RECOMMENDED | $141,872 | $210,427 |
$100,380
1,654,482
kWh
|
$22,403
-
kW-mo/yr
|
$18,884
-
MMBtu
|
$105 | $100 | ||
| TOTAL IMPLEMENTED | $141,872 | $210,427 |
$100,380
1,654,482
kWh
|
$22,403
-
kW-mo/yr
|
$18,884
-
MMBtu
|
$105 | $100 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs