ITAC Assessment: AT0023
ITAC logo
ITAC Assessment: AT0023
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1985
Principal Product TAGS & LABELS
NAICS
n/a
SIC 2679: Converted Paper and Paperboard Products, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 80
Plant Area
n/a
Annual Production 25,000,000
pieces
Production Hrs. Annual 4,000
hrs
Location (State) North Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $36,735 675,557
kWh
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $5,751 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $3,941

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.4133: Use most efficient type of electric motors $93 $255 $93
1,758
kWh
02 2.7142: Utilize higher efficiency lamps and/or ballasts $127 $270 $127
2,345
kWh
03 2.7142: Utilize higher efficiency lamps and/or ballasts $1,249 $218 $1,249
23,154
kWh
04 2.4221: Install compressor air intakes in coolest locations $156 $250 $156
2,931
kWh
05 2.7142: Utilize higher efficiency lamps and/or ballasts $341 $125 $341
6,448
kWh
06 2.7226: Use computer programs to optimize hvac performance $3,785 $2,700 $3,785
70,047
kWh
TOTAL RECOMMENDED $5,751 $3,818 $5,751
106,683
kWh
TOTAL IMPLEMENTED $3,941 $2,950 $3,941
72,978
kWh
Yearly Savings* Imp'd Cost* Electricity Usage Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs