ITAC Assessment: AT0022
ITAC logo
ITAC Assessment: AT0022
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1985
Principal Product CORRUCATED SHEETS
NAICS
n/a
SIC 2679: Converted Paper and Paperboard Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 80
Plant Area
n/a
Annual Production 684
thousand feet
Production Hrs. Annual 6,240
hrs
Location (State) North Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $66,897 1,441,970
kWh
Natural Gas $174,920 35,567
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $23,475 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $23,475

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.4133: Use most efficient type of electric motors $449 $422 $449
9,672
kWh
-
02 2.1233: Analyze flue gas for proper air/fuel ratio $17,673 $300 - $17,673
-
MMBtu
03 2.4231: Reduce the pressure of compressed air to the minimum required $394 - $394
8,499
kWh
-
04 2.4221: Install compressor air intakes in coolest locations $272 $250 $272
5,862
kWh
-
05 2.7226: Use computer programs to optimize hvac performance $830 $450 $830
17,878
kWh
-
06 2.2122: Install / repair insulation on condensate lines $2,293 $1,920 - $2,293
-
MMBtu
07 2.7142: Utilize higher efficiency lamps and/or ballasts $1,564 $205 $1,564
33,705
kWh
-
TOTAL RECOMMENDED $23,475 $3,547 $3,509
75,616
kWh
$19,966
-
MMBtu
TOTAL IMPLEMENTED $23,475 $3,547 $3,509
75,616
kWh
$19,966
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs