ITAC Assessment: AT0021
ITAC logo
ITAC Assessment: AT0021
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1985
Principal Product OFFICE FURNITURE
NAICS
n/a
SIC 2521: Wood Office Furniture
Sales Range $10
M
to 50
M
# of Employees 285
Plant Area
n/a
Annual Production 150,000
pieces
Production Hrs. Annual 2,500
hrs
Location (State) North Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $55,500 891,852
kWh
Natural Gas $18,419 2,946
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $4,981 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $3,902

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.4133: Use most efficient type of electric motors $191 $324 $191
2,931
kWh
02 2.7226: Use computer programs to optimize hvac performance $888 $1,050 $888
14,361
kWh
03 2.4231: Reduce the pressure of compressed air to the minimum required $421 - $421
6,741
kWh
04 2.4221: Install compressor air intakes in coolest locations $274 $500 $274
4,396
kWh
05 2.7142: Utilize higher efficiency lamps and/or ballasts $227 $270 $227
3,810
kWh
06 2.7142: Utilize higher efficiency lamps and/or ballasts $277 $150 $277
4,396
kWh
07 2.7142: Utilize higher efficiency lamps and/or ballasts $2,703 $658 $2,703
43,669
kWh
TOTAL RECOMMENDED $4,981 $2,952 $4,981
80,304
kWh
TOTAL IMPLEMENTED $3,902 $1,578 $3,902
63,012
kWh
Yearly Savings* Imp'd Cost* Electricity Usage Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs