ITAC Assessment: AS0622
ITAC logo
ITAC Assessment: AS0622
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2026
Principal Product wastewater treatment
NAICS 221320: Sewage Treatment Facilities
SIC 4952: Sewerage Systems
Sales Range less than $500
k
# of Employees 7
Plant Area 26,140,000
ft2
Annual Production 4,000
Tgal
Production Hrs. Annual 8,760
hrs
Location (State) Arizona

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $173,550 2,042,444
kWh
Electricity Demand $33,411 3,838
kW-mo/yr
Electricity Fees $24,393 -
Fuel Oil #2 $40,944 1,956
MMBtu
Other Gas $6,033 1
MMBtu
TOTAL YEARLY COSTS $278,331
RECOMMENDED SAVINGS* $223,469 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Fuel Oil #2 Savings Personnel Changes Savings One-time Revenue or Avoided Cost Savings By-product Production Savings
01 2.5194: Redesign process $121,581 $296,526 $(-22,811.0)
(-268,370)
kWh
$(-1,201.0)
-
kW-mo/yr
- $35,163
-
MMBtu
- - $110,430
02 2.4321: Upgrade obsolete equipment $92,326 $209,030 - - - $(-519.0)
-
MMBtu
$(-36,370.0) - $129,215
03 2.8121: Apply for tax-free status for energy purchases $6,044 $1,600 - - - - - $6,044 -
04 2.4323: Use optimum size and capacity equipment $1,811 $889 $1,588
18,682
kWh
$223
-
kW-mo/yr
- - - - -
05 2.8112: Combine utility meters $1,018 $6,134 - $252
-
kW-mo/yr
$766 - - - -
06 2.6232: Install set-back timers $465 $175 $388
4,563
kWh
$77
-
kW-mo/yr
- - - - -
07 2.7272: Install heat pipes / raise cooling setpoint $224 $25 $133
1,561
kWh
$91
-
kW-mo/yr
- - - - -
TOTAL RECOMMENDED $223,469 $514,379 $(-20,702.0)
(-243,564)
kWh
$(-558.0)
-
kW-mo/yr
$766 $34,644
-
MMBtu
$(-36,370.0) $6,044 $239,645
TOTAL IMPLEMENTED - - - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Fuel Oil #2 Savings Personnel Changes Savings One-time Revenue or Avoided Cost Savings By-product Production Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs