| Assessment Year | 2026 |
|---|---|
| Principal Product | Metal, plastic, Fiber, Foam repurposing |
| NAICS | 339999: All Other Miscellaneous Manufacturing |
| SIC | 3999: Manufacturing Industries, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 50 |
| Plant Area |
225,000
ft2
|
| Annual Production | 65,000,000
lb
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Arizona |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $9,304 | 234,800 |
kWh
|
$0.040 |
| Electricity Demand | $21,501 | 1,460 |
kW-mo/yr
|
$14.73 |
| Electricity Fees | $4,427 | - |
|
- |
| Fuel Oil #2 | $182,791 | 7,937 |
MMBtu
|
$23.03 |
| Other Energy | $29,989 | 1 |
MMBtu
|
$29,989.00 |
| TOTAL YEARLY COSTS | $248,012 | |||
| RECOMMENDED SAVINGS* | $51,724 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #2 Savings | Administrative Changes Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.8226: Increase efficiency of trucks | $18,148 | $80,584 | - | - |
$18,148
-
MMBtu
|
- | - | |
| 02 | 2.1321: Replace fossil fuel equipment with electrical equipment | $12,397 | $250,000 |
$(-8,557.0)
(-216,080)
kWh
|
$(-4,395.0)
-
kW-mo/yr
|
$23,099
-
MMBtu
|
$2,250 | - | |
| 03 | 2.1331: Burn a less expensive grade of fuel | $9,381 | $6,914 | - | - | - | - | $9,381 | |
| 04 | 2.8223: Add air shields to trucks to increase fuel mileage | $8,752 | $14,707 | - | - |
$8,752
-
MMBtu
|
- | - | |
| 05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $1,050 | $1,691 |
$730
18,441
kWh
|
$320
-
kW-mo/yr
|
- | - | - | |
| 06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $906 | $178 |
$600
15,142
kWh
|
$306
-
kW-mo/yr
|
- | - | - | |
| 07 | 2.6231: Utilize controls to operate equipment only when needed | $488 | $586 |
$394
9,958
kWh
|
$94
-
kW-mo/yr
|
- | - | - | |
| 08 | 2.6125: Keep equipment clean | $466 | $1,354 |
$466
11,757
kWh
|
- | - | - | - | |
| 09 | 2.7421: Reduce glazed areas in buildings | $69 | $769 |
$47
1,177
kWh
|
$22
-
kW-mo/yr
|
- | - | - | |
| 10 | 2.7491: Insulate glazing, walls, ceilings, and roofs | $67 | $728 |
$32
808
kWh
|
$35
-
kW-mo/yr
|
- | - | - | |
| TOTAL RECOMMENDED | $51,724 | $357,511 |
$(-6,288.0)
(-158,797)
kWh
|
$(-3,618.0)
-
kW-mo/yr
|
$49,999
-
MMBtu
|
$2,250 | $9,381 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #2 Savings | Administrative Changes Savings | One-time Revenue or Avoided Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs