ITAC Assessment: AS0617
ITAC logo
ITAC Assessment: AS0617
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2026
Principal Product wastewater treatment
NAICS 221320: Sewage Treatment Facilities
SIC 4952: Sewerage Systems
Sales Range less than $500
k
# of Employees 30
Plant Area 13,000
ft2
Annual Production 730,000
Tgal
Production Hrs. Annual 8,760
hrs
Location (State) Arizona

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $242,886 2,528,760
kWh
Electricity Demand $31,063 6,363
kW-mo/yr
Electricity Fees $29,422 -
TOTAL YEARLY COSTS $303,371
RECOMMENDED SAVINGS* $275,637 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Primary Raw Material Savings Ancillary Material Cost Savings
01 2.4322: Use or replace with energy efficient substitutes $168,194 $740,702 $115,051
1,198,448
kWh
$8,297
-
kW-mo/yr
$45,835 $(-989.0)
02 2.6231: Utilize controls to operate equipment only when needed $48,164 $4,095 $47,817
498,097
kWh
$3,432
-
kW-mo/yr
- $(-3,085.0)
03 2.9114: Use solar heat to make electricty $46,576 $364,318 $51,278
534,145
kWh
$366
-
kW-mo/yr
- $(-5,068.0)
04 2.3141: Use battery storage for demand control $4,794 $41,498 - $5,544
-
kW-mo/yr
- $(-750.0)
05 2.6232: Install set-back timers $3,886 $566 $3,814
39,729
kWh
$72
-
kW-mo/yr
- -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $2,401 $6,692 $1,806
18,804
kWh
$327
-
kW-mo/yr
- $268
07 2.7135: Install occupancy sensors $960 $1,199 $810
8,439
kWh
$150
-
kW-mo/yr
- -
08 2.7272: Install heat pipes / raise cooling setpoint $662 $76 $581
6,053
kWh
$81
-
kW-mo/yr
- -
TOTAL RECOMMENDED $275,637 $1,159,146 $221,157
2,303,715
kWh
$18,269
-
kW-mo/yr
$45,835 $(-9,624.0)
TOTAL IMPLEMENTED - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Primary Raw Material Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs