| Assessment Year | 2026 |
|---|---|
| Principal Product | wastewater treatment |
| NAICS | 221320: Sewage Treatment Facilities |
| SIC | 4952: Sewerage Systems |
| Sales Range | less than $500 k |
| # of Employees | 30 |
| Plant Area |
13,000
ft2
|
| Annual Production | 730,000
Tgal
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Arizona |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $242,886 | 2,528,760 |
kWh
|
$0.096 |
| Electricity Demand | $31,063 | 6,363 |
kW-mo/yr
|
$4.88 |
| Electricity Fees | $29,422 | - |
|
- |
| TOTAL YEARLY COSTS | $303,371 | |||
| RECOMMENDED SAVINGS* | $275,637 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Primary Raw Material Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.4322: Use or replace with energy efficient substitutes | $168,194 | $740,702 |
$115,051
1,198,448
kWh
|
$8,297
-
kW-mo/yr
|
$45,835 | $(-989.0) | |
| 02 | 2.6231: Utilize controls to operate equipment only when needed | $48,164 | $4,095 |
$47,817
498,097
kWh
|
$3,432
-
kW-mo/yr
|
- | $(-3,085.0) | |
| 03 | 2.9114: Use solar heat to make electricty | $46,576 | $364,318 |
$51,278
534,145
kWh
|
$366
-
kW-mo/yr
|
- | $(-5,068.0) | |
| 04 | 2.3141: Use battery storage for demand control | $4,794 | $41,498 | - |
$5,544
-
kW-mo/yr
|
- | $(-750.0) | |
| 05 | 2.6232: Install set-back timers | $3,886 | $566 |
$3,814
39,729
kWh
|
$72
-
kW-mo/yr
|
- | - | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,401 | $6,692 |
$1,806
18,804
kWh
|
$327
-
kW-mo/yr
|
- | $268 | |
| 07 | 2.7135: Install occupancy sensors | $960 | $1,199 |
$810
8,439
kWh
|
$150
-
kW-mo/yr
|
- | - | |
| 08 | 2.7272: Install heat pipes / raise cooling setpoint | $662 | $76 |
$581
6,053
kWh
|
$81
-
kW-mo/yr
|
- | - | |
| TOTAL RECOMMENDED | $275,637 | $1,159,146 |
$221,157
2,303,715
kWh
|
$18,269
-
kW-mo/yr
|
$45,835 | $(-9,624.0) | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Primary Raw Material Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs