Assessment Year | 2024 |
---|---|
Principal Product | Portland Cement |
NAICS | 327310: Cement Manufacturing |
SIC | 3241: Cement, Hydraulic |
Sales Range | $50 M to 100M |
# of Employees | 130 |
Plant Area |
1,336,000
ft2
|
Annual Production | 660,000
ton
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Arizona |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $3,777,130 | 85,896,950 |
kWh
|
$0.044 |
Electricity Demand | $1,749,688 | 298,923 |
kW-mo/yr
|
$5.85 |
Electricity Fees | $24,567 | - |
|
- |
Natural Gas | $5,718,157 | 1,794,636 |
MMBtu
|
$3.19 |
TOTAL YEARLY COSTS | $11,269,542 | |||
RECOMMENDED SAVINGS* | $188,249 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $126,717 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $81,526 | $55,952 |
$68,962
1,567,337
kWh
|
$12,564
-
kW-mo/yr
|
- | - | - | |
02 | 2.4224: Upgrade controls on compressors | $61,102 | $20,000 |
$51,688
1,174,716
kWh
|
$9,414
-
kW-mo/yr
|
- | - | - | |
03 | 4.821: Pay bills on time to avoid late fees | $22,882 | $38 | - | - | - | - | $22,882 | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $16,525 | $34,427 |
$17,070
387,933
kWh
|
$3,108
-
kW-mo/yr
|
- | $(-3,653.0) | - | |
05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $5,292 | $908 | - | - | - | - | $5,292 | |
06 | 2.3137: Use power during off-peak periods | $492 | $511 | - | - | $492 | - | - | |
07 | 2.7132: Install timers on light switches in little used areas | $430 | $987 |
$430
9,780
kWh
|
- | - | - | - | |
TOTAL RECOMMENDED | $188,249 | $112,823 |
$138,150
3,139,766
kWh
|
$25,086
-
kW-mo/yr
|
$492 | $(-3,653.0) | $28,174 | ||
TOTAL IMPLEMENTED | $126,717 | $91,836 |
$86,032
1,955,270
kWh
|
$15,672
-
kW-mo/yr
|
$492 | $(-3,653.0) | $28,174 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs