ITAC Assessment: AS0567
ITAC logo
ITAC Assessment: AS0567
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2024
Principal Product bottled and canned drinks
NAICS 312111: Soft Drink Manufacturing
SIC 2086: Bottled and Canned Soft Drinks and Carbonated Waters
Sales Range $50
M
to 100
M
# of Employees 500
Plant Area 600,000
ft2
Annual Production 40,000,000
units
Production Hrs. Annual 8,760
hrs
Location (State) Arizona

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,148,336 16,238,303
kWh
Electricity Demand $264,111 35,323
kW-mo/yr
Electricity Fees $32,909 -
Natural Gas $315,616 27,229
MMBtu
Waste Disposal Costs
Water Usage $586,574 172,575
Tgal
TOTAL YEARLY COSTS $2,347,546
RECOMMENDED SAVINGS* $253,260 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $100,430

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.9114: Use solar heat to make electricty $100,430 $774,239 $81,551
1,153,477
kWh
$18,879
-
kW-mo/yr
02 4.611: Begin a practice of predictive / preventative maintenance $86,125 $165,996 $86,125
1,219,448
kWh
-
03 2.4224: Upgrade controls on compressors $57,803 $10,720 $50,299
711,450
kWh
$7,504
-
kW-mo/yr
04 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $8,255 $31,926 $6,468
91,489
kWh
$1,787
-
kW-mo/yr
05 2.6211: Conserve energy by efficient use of vending machines $647 $384 $557
7,884
kWh
$90
-
kW-mo/yr
TOTAL RECOMMENDED $253,260 $983,265 $225,000
3,183,748
kWh
$28,260
-
kW-mo/yr
TOTAL IMPLEMENTED $100,430 $774,239 $81,551
1,153,477
kWh
$18,879
-
kW-mo/yr
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs