| Assessment Year | 2023 |
|---|---|
| Principal Product | Social Services & Food Distribution |
| NAICS | 624210: Community Food Services |
| SIC | 8399: Social Services, Not Elsewhere Classified |
| Sales Range | $1 M to 5M |
| # of Employees | 200 |
| Plant Area |
88,519
ft2
|
| Annual Production | 1,600,000
units
|
| Production Hrs. Annual | 4,380
hrs
|
| Location (State) | Arizona |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $92,354 | 1,797,587 |
kWh
|
$0.051 | |
| Electricity Demand | $15,402 | 2,172 |
kW-mo/yr
|
$7.09 | |
| Electricity Fees | $104,724 | - |
|
- | |
| Waste Disposal Costs | |||||
| Water Usage | $23,856 | 4,353 |
Tgal
|
$5.48 | |
| TOTAL YEARLY COSTS | $236,336 | ||||
| RECOMMENDED SAVINGS* | $61,507 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $60,558 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.1321: Replace fossil fuel equipment with electrical equipment | $41,664 | $123,750 |
$(-13,214.0)
(-259,105)
kWh
|
$(-3,985.0)
-
kW-mo/yr
|
$58,863
-
MMBtu
|
- | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $15,226 | $17,834 |
$9,982
195,730
kWh
|
$1,911
-
kW-mo/yr
|
- | $3,333 | |
| 03 | 2.7132: Install timers on light switches in little used areas | $3,340 | $6,151 |
$3,340
65,495
kWh
|
- | - | - | |
| 04 | 2.7144: Install spectral reflectors / delamp | $800 | $685 |
$746
14,619
kWh
|
$54
-
kW-mo/yr
|
- | - | |
| 05 | 2.7261: Install timers and/or thermostats | $328 | $540 |
$328
6,421
kWh
|
- | - | - | |
| 06 | 2.7135: Install occupancy sensors | $149 | $277 |
$123
2,404
kWh
|
$26
-
kW-mo/yr
|
- | - | |
| TOTAL RECOMMENDED | $61,507 | $149,237 |
$1,305
25,564
kWh
|
$(-1,994.0)
-
kW-mo/yr
|
$58,863
-
MMBtu
|
$3,333 | ||
| TOTAL IMPLEMENTED | $60,558 | $148,275 |
$436
8,541
kWh
|
$(-2,074.0)
-
kW-mo/yr
|
$58,863
-
MMBtu
|
$3,333 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs