Assessment Year | 2023 |
---|---|
Principal Product | treated wastewater |
NAICS | 221320: Sewage Treatment Facilities |
SIC | 4952: Sewerage Systems |
Sales Range | less than $500 k |
# of Employees | 9 |
Plant Area |
10,773
ft2
|
Annual Production | 8,000
Tgal
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | New Mexico |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $76,180 | 907,100 |
kWh
|
$0.084 |
Electricity Demand | $28,928 | 3,277 |
kW-mo/yr
|
$8.83 |
TOTAL YEARLY COSTS | $105,108 | |||
RECOMMENDED SAVINGS* | $19,254 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $3,753 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|
01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $15,420 | $76,246 |
$11,102
132,161
kWh
|
$4,318
-
kW-mo/yr
|
- | |
02 | 2.7229: Air condition only space necessary | $1,804 | $8,019 |
$1,874
22,312
kWh
|
$(-70.0)
-
kW-mo/yr
|
- | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,306 | $2,116 |
$779
9,283
kWh
|
$473
-
kW-mo/yr
|
$54 | |
04 | 2.7221: Lower temperature during the winter season and vice-versa | $493 | $25 |
$280
3,329
kWh
|
$213
-
kW-mo/yr
|
- | |
05 | 2.7444: Close holes and openings in building such as broken windows | $150 | $92 |
$88
1,043
kWh
|
$62
-
kW-mo/yr
|
- | |
06 | 2.7132: Install timers on light switches in little used areas | $81 | $222 |
$81
966
kWh
|
- | - | |
TOTAL RECOMMENDED | $19,254 | $86,720 |
$14,204
169,094
kWh
|
$4,996
-
kW-mo/yr
|
$54 | ||
TOTAL IMPLEMENTED | $3,753 | $10,252 |
$3,021
35,967
kWh
|
$678
-
kW-mo/yr
|
$54 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs