ITAC Assessment: AS0532
ITAC logo
ITAC Assessment: AS0532
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2022
Principal Product Office Building
NAICS 551114: Corporate, Subsidiary, and Regional Managing Offices
SIC 7389: Business Services, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 8
Plant Area 25,000
ft2
Annual Production 1
units
Production Hrs. Annual 3,120
hrs
Location (State) Arizona

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $19,498 250,680
kWh
Electricity Demand $4,093 1,372
kW-mo/yr
Electricity Fees $2,641 -
TOTAL YEARLY COSTS $26,232
RECOMMENDED SAVINGS* $18,014 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Ancillary Material Cost Savings
01 2.7229: Air condition only space necessary $5,668 $800 $3,129
40,874
kWh
$2,539
-
kW-mo/yr
-
02 2.9114: Use solar heat to make electricty $6,151 $182,215 $5,733
73,496
kWh
$418
-
kW-mo/yr
-
03 2.7142: Utilize higher efficiency lamps and/or ballasts $2,744 $6,177 $1,842
23,619
kWh
$151
-
kW-mo/yr
$751
04 2.7132: Install timers on light switches in little used areas $2,148 $2,555 $2,148
27,538
kWh
- -
05 2.7444: Close holes and openings in building such as broken windows $533 $158 $467
5,988
kWh
$66
-
kW-mo/yr
-
06 2.6218: Turn off equipment when not in use $490 $300 $473
6,063
kWh
$17
-
kW-mo/yr
-
07 2.6218: Turn off equipment when not in use $230 $25 $219
2,803
kWh
$11
-
kW-mo/yr
-
08 2.7135: Install occupancy sensors $50 $138 $47
601
kWh
$3
-
kW-mo/yr
-
TOTAL RECOMMENDED $18,014 $192,368 $14,058
180,982
kWh
$3,205
-
kW-mo/yr
$751
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs