ITAC Assessment: AS0527
ITAC logo
ITAC Assessment: AS0527
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2022
Principal Product Refrigerated warehousing and storage
NAICS 493120: Refrigerated Warehousing and Storage
SIC 4222: Refrigerated Warehousing and Storage
Sales Range $1
M
to 5
M
# of Employees 8
Plant Area 5,500
ft2
Annual Production 1
units
Production Hrs. Annual 2,762
hrs
Location (State) Arizona

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $8,933 109,305
kWh
Electricity Demand $2,252 273
kW-mo/yr
Electricity Fees $3,419 -
TOTAL YEARLY COSTS $14,604
RECOMMENDED SAVINGS* $3,948 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $3,948

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Ancillary Material Cost Savings By-product Production Savings
01 4.621: Use fixtures to reduce machine changeout times $1,896 $1,099 $(-2,485.0)
(-30,420)
kWh
$(-619.0)
-
kW-mo/yr
- $5,000
02 2.4133: Use most efficient type of electric motors $1,264 $2,187 $896
10,967
kWh
$368
-
kW-mo/yr
- -
03 2.7444: Close holes and openings in building such as broken windows $638 $115 $452
5,529
kWh
$186
-
kW-mo/yr
- -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $150 $317 $118
1,446
kWh
$21
-
kW-mo/yr
$11 -
TOTAL RECOMMENDED $3,948 $3,718 $(-1,019.0)
(-12,478)
kWh
$(-44.0)
-
kW-mo/yr
$11 $5,000
TOTAL IMPLEMENTED $3,948 $3,718 $(-1,019.0)
(-12,478)
kWh
$(-44.0)
-
kW-mo/yr
$11 $5,000
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs