| Assessment Year | 2018 |
|---|---|
| Principal Product | Capacitors |
| NAICS | 334416: Capacitor, Resistor, Coil, Transformer, and Other Inductor Manufacturing |
| SIC | 3675: Electronic Capacitors |
| Sales Range | $5 M to 10M |
| # of Employees | 30 |
| Plant Area |
10,000
ft2
|
| Annual Production | 500,000
units
|
| Production Hrs. Annual | 3,328
hrs
|
| Location (State) | Arizona |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $56,128 | 444,687 |
kWh
|
$0.13 |
| Electricity Demand | $12,587 | 1,777 |
kW-mo/yr
|
$7.08 |
| Electricity Fees | $7,293 | - |
|
- |
| TOTAL YEARLY COSTS | $76,008 | |||
| RECOMMENDED SAVINGS* | $20,138 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
|---|---|---|---|---|---|---|
| 01 | 2.6232: Install set-back timers | $7,726 | $83 |
$7,726
61,320
kWh
|
- | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,598 | $5,816 |
$2,878
22,845
kWh
|
$720
-
kW-mo/yr
|
|
| 03 | 2.7232: Replace existing hvac unit with high efficiency model | $4,076 | $18,560 |
$3,311
26,280
kWh
|
$765
-
kW-mo/yr
|
|
| 04 | 2.7135: Install occupancy sensors | $2,232 | $1,350 |
$2,232
17,714
kWh
|
- | |
| 05 | 2.4133: Use most efficient type of electric motors | $1,699 | $685 |
$1,413
11,216
kWh
|
$286
-
kW-mo/yr
|
|
| 06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $433 | $240 |
$361
2,865
kWh
|
$72
-
kW-mo/yr
|
|
| 07 | 2.2511: Insulate bare equipment | $374 | $55 |
$348
2,759
kWh
|
$26
-
kW-mo/yr
|
|
| TOTAL RECOMMENDED | $20,138 | $26,789 |
$18,269
144,999
kWh
|
$1,869
-
kW-mo/yr
|
||
| TOTAL IMPLEMENTED | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs