Assessment Year | 2017 |
---|---|
Principal Product | Precision metal parts, milled and ground to customer specifications |
NAICS | 334418: Printed Circuit Assembly (Electronic Assembly) Manufacturing |
SIC | 3559: Special Industry Machinery, Not Elsewhere Classified |
Sales Range | $50 M to 100M |
# of Employees | 150 |
Plant Area |
45,000
ft2
|
Annual Production | 100,000
units
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Arizona |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $245,067 | 4,114,169 |
kWh
|
$0.060 |
Electricity Demand | $52,783 | 23,443 |
kW-mo/yr
|
$2.25 |
Electricity Fees | $108,273 | - |
|
- |
TOTAL YEARLY COSTS | $406,124 | |||
RECOMMENDED SAVINGS* | $133,523 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $307 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
---|---|---|---|---|---|---|
01 | 2.4224: Upgrade controls on compressors | $68,034 | $6,582 |
$66,620
693,950
kWh
|
$1,414
-
kW-mo/yr
|
|
02 | 2.4224: Upgrade controls on compressors | $43,502 | $4,394 |
$41,480
370,360
kWh
|
$2,022
-
kW-mo/yr
|
|
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $11,405 | $1,200 |
$11,108
115,710
kWh
|
$297
-
kW-mo/yr
|
|
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $7,250 | $2,513 |
$7,072
73,668
kWh
|
$178
-
kW-mo/yr
|
|
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,564 | $60 |
$2,415
21,563
kWh
|
$149
-
kW-mo/yr
|
|
06 | 2.6242: Minimize operation of equipment maintained in standby condition | $461 | $450 |
$461
4,803
kWh
|
- | |
07 | 2.6212: Turn off equipment during breaks, reduce operating time | $307 | $60 |
$307
3,197
kWh
|
- | |
TOTAL RECOMMENDED | $133,523 | $15,259 |
$129,463
1,283,251
kWh
|
$4,060
-
kW-mo/yr
|
||
TOTAL IMPLEMENTED | $307 | $60 |
$307
3,197
kWh
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs