Assessment Year | 2023 |
---|---|
Principal Product | Vehicle Engines |
NAICS | 336310: Motor Vehicle Gasoline Engine and Engine Parts Manufacturing |
SIC | 3714: Motor Vehicle Parts and Accessories |
Sales Range | $10 M to 50M |
# of Employees | 50 |
Plant Area |
100,000
ft2
|
Annual Production | 12,400
units
|
Production Hrs. Annual | 2,000
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $51,827 | 735,438 |
kWh
|
$0.070 | |
Electricity Demand | $21,663 | 3,819 |
kW-mo/yr
|
$5.67 | |
Electricity Fees | $553 | - |
|
- | |
Natural Gas | $18,917 | 2,709 |
MMBtu
|
$6.98 | |
Waste Disposal Costs | |||||
Water Usage | $4,260 | 970 |
Tgal
|
$4.39 | |
Water Disposal | $5,162 | 970 |
Tgal
|
$5.32 | |
TOTAL YEARLY COSTS | $102,382 | ||||
RECOMMENDED SAVINGS* | $13,950 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $3,983 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $139 | - |
$112
1,585
kWh
|
$27
-
kW-mo/yr
|
- | - | - | - | |
02 | 2.7224: Reduce space conditioning during non-working hours | $3,987 | $912 |
$1,031
14,547
kWh
|
- | - |
$2,956
-
MMBtu
|
- | - | |
03 | 2.4239: Eliminate or reduce compressed air usage | $2,251 | $772 |
$31
434
kWh
|
$2,220
-
kW-mo/yr
|
- | - | - | - | |
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $653 | - |
$450
6,343
kWh
|
$203
-
kW-mo/yr
|
- | - | - | - | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $300 | $952 |
$202
2,870
kWh
|
$98
-
kW-mo/yr
|
- | - | - | - | |
06 | 2.3212: Optimize plant power factor | $2,184 | $2,800 | - | - | $2,184 | - | - | - | |
07 | 2.2628: Utilize a less expensive cooling method | $892 | $1,613 |
$892
12,656
kWh
|
- | - | - | - | - | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,544 | $17,274 |
$1,473
20,888
kWh
|
$711
-
kW-mo/yr
|
- | - | $476 | $884 | |
TOTAL RECOMMENDED | $13,950 | $24,323 |
$4,191
59,323
kWh
|
$3,259
-
kW-mo/yr
|
$2,184 |
$2,956
-
MMBtu
|
$476 | $884 | ||
TOTAL IMPLEMENTED | $3,983 | $18,226 |
$1,787
25,343
kWh
|
$836
-
kW-mo/yr
|
- | - | $476 | $884 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs