ITAC Assessment: AS0429
ITAC logo
ITAC Assessment: AS0429
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2006
Principal Product Natural fiber insulation
NAICS 327993: Mineral Wool Manufacturing
SIC 3296: Mineral Wool
Sales Range $1
M
to 5
M
# of Employees 20
Plant Area 250,000
ft2
Annual Production 2,000
thousand feet
Production Hrs. Annual 2,080
hrs
Location (State) Arizona

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $72,229 731,200
kWh
Natural Gas $49,268 4,323
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $5,888 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.1233: Analyze flue gas for proper air/fuel ratio $2,688 $1,000 - $2,688
-
MMBtu
02 2.2511: Insulate bare equipment $2,039 $500 - $2,039
-
MMBtu
03 2.4231: Reduce the pressure of compressed air to the minimum required $1,127 $1,000 $1,127
11,383
kWh
-
04 2.4323: Use optimum size and capacity equipment $34 $3,200 $34
3,462
kWh
-
TOTAL RECOMMENDED $5,888 $5,700 $1,161
14,845
kWh
$4,727
-
MMBtu
TOTAL IMPLEMENTED - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs