| Assessment Year | 2006 |
|---|---|
| Principal Product | Printed circuit boards |
| NAICS | 334412: Bare Printed Circuit Board Manufacturing |
| SIC | 3672: Printed Circuit Boards |
| Sales Range | $50 M to 100M |
| # of Employees | 150 |
| Plant Area |
180,000
ft2
|
| Annual Production | 0
units
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Arizona |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $697,736 | 6,679,462 |
kWh
|
$0.10 |
| Electricity Demand | $61,550 | 5,796 |
kW-mo/yr
|
$10.62 |
| Natural Gas | $28,886 | 31,921 |
MMBtu
|
$0.90 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $61,613 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $30,850 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.2614: Use cooling tower or economizer to replace chiller cooling | $10,102 | $17,458 |
$2,463
23,568
kWh
|
$7,639
-
kW-mo/yr
|
- | |
| 02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $9,823 | $500 |
$8,282
79,250
kWh
|
$1,541
-
kW-mo/yr
|
- | |
| 03 | 2.2511: Insulate bare equipment | $8,267 | $2,077 | - | - |
$8,267
-
MMBtu
|
|
| 04 | 2.4224: Upgrade controls on compressors | $7,727 | $5,500 |
$6,514
62,332
kWh
|
$1,213
-
kW-mo/yr
|
- | |
| 05 | 2.2531: Re-size charging openings or add movable cover or door | $6,172 | $2,000 |
$4,441
42,502
kWh
|
$1,731
-
kW-mo/yr
|
- | |
| 06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $5,221 | $1,000 |
$5,221
49,962
kWh
|
- | - | |
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $7,539 | $15,085 |
$6,309
60,393
kWh
|
$1,230
-
kW-mo/yr
|
- | |
| 08 | 2.4323: Use optimum size and capacity equipment | $3,590 | $20,832 |
$3,009
28,796
kWh
|
$581
-
kW-mo/yr
|
- | |
| 09 | 2.9112: Use solar heat to heat water | $3,172 | $14,400 |
$3,136
4,801
kWh
|
$36
-
kW-mo/yr
|
- | |
| TOTAL RECOMMENDED | $61,613 | $78,852 |
$39,375
351,604
kWh
|
$13,971
-
kW-mo/yr
|
$8,267
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $30,850 | $18,662 |
$19,812
189,605
kWh
|
$2,771
-
kW-mo/yr
|
$8,267
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs