ITAC Assessment: AS0395
ITAC logo
ITAC Assessment: AS0395
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2005
Principal Product Aircraft evacuation slides and rafts
NAICS 336413: Other Aircraft Parts and Auxiliary Equipment Manufacturing
SIC 3728: Aircraft Parts and Auxiliary Equipment, Not Elsewhere Classified
Sales Range $50
M
to 100
M
# of Employees 465
Plant Area 283,000
ft2
Annual Production 1,900
pieces
Production Hrs. Annual 2,510
hrs
Location (State) Arizona

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $258,925 4,384,680
kWh
Electricity Demand $28,331 11,074
kW-mo/yr
Electricity Fees $22,098 -
Natural Gas $76,000 9,488
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $18,702 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $9,874

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings
01 2.4224: Upgrade controls on compressors $5,134 $10,000 $4,718
79,901
kWh
$416
-
kW-mo/yr
-
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,439 $1,000 $3,173
53,740
kWh
$266
-
kW-mo/yr
-
03 2.7135: Install occupancy sensors $429 $1,950 $429
8,328
kWh
- -
04 2.4231: Reduce the pressure of compressed air to the minimum required $872 $800 $722
12,323
kWh
$150
-
kW-mo/yr
-
05 2.9112: Use solar heat to heat water $1,228 $1,100 $1,228
18,921
kWh
- -
06 3.1175: Use a different or recycled raw material $7,600 $380 - - $7,600
-
lb
TOTAL RECOMMENDED $18,702 $15,230 $10,270
173,213
kWh
$832
-
kW-mo/yr
$7,600
-
lb
TOTAL IMPLEMENTED $9,874 $13,750 $9,042
154,292
kWh
$832
-
kW-mo/yr
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs