| Assessment Year | 2005 |
|---|---|
| Principal Product | Aircraft evacuation slides and rafts |
| NAICS | 336413: Other Aircraft Parts and Auxiliary Equipment Manufacturing |
| SIC | 3728: Aircraft Parts and Auxiliary Equipment, Not Elsewhere Classified |
| Sales Range | $50 M to 100M |
| # of Employees | 465 |
| Plant Area |
283,000
ft2
|
| Annual Production | 1,900
pieces
|
| Production Hrs. Annual | 2,510
hrs
|
| Location (State) | Arizona |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $258,925 | 4,384,680 |
kWh
|
$0.059 |
| Electricity Demand | $28,331 | 11,074 |
kW-mo/yr
|
$2.56 |
| Electricity Fees | $22,098 | - |
|
- |
| Natural Gas | $76,000 | 9,488 |
MMBtu
|
$8.01 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $18,702 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $9,874 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4224: Upgrade controls on compressors | $5,134 | $10,000 |
$4,718
79,901
kWh
|
$416
-
kW-mo/yr
|
- | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,439 | $1,000 |
$3,173
53,740
kWh
|
$266
-
kW-mo/yr
|
- | |
| 03 | 2.7135: Install occupancy sensors | $429 | $1,950 |
$429
8,328
kWh
|
- | - | |
| 04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $872 | $800 |
$722
12,323
kWh
|
$150
-
kW-mo/yr
|
- | |
| 05 | 2.9112: Use solar heat to heat water | $1,228 | $1,100 |
$1,228
18,921
kWh
|
- | - | |
| 06 | 3.1175: Use a different or recycled raw material | $7,600 | $380 | - | - |
$7,600
-
lb
|
|
| TOTAL RECOMMENDED | $18,702 | $15,230 |
$10,270
173,213
kWh
|
$832
-
kW-mo/yr
|
$7,600
-
lb
|
||
| TOTAL IMPLEMENTED | $9,874 | $13,750 |
$9,042
154,292
kWh
|
$832
-
kW-mo/yr
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs