| Assessment Year | 2004 |
|---|---|
| Principal Product | Pork Products |
| NAICS | 112210: Hog and Pig Farming |
| SIC | 2013: Sausages and Other Prepared Meat Products |
| Sales Range | $50 M to 100M |
| # of Employees | 140 |
| Plant Area |
70,000
ft2
|
| Annual Production | 750,000
pieces
|
| Production Hrs. Annual | 2,860
hrs
|
| Location (State) | Iowa |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $119,153 | 4,172,000 |
kWh
|
$0.029 |
| Electricity Demand | $89,078 | 9,408 |
kW-mo/yr
|
$9.47 |
| Electricity Fees | $16,557 | - |
|
- |
| Natural Gas | $313,075 | 61,187 |
MMBtu
|
$5.12 |
| LPG | $18,745 | 3,671 |
MMBtu
|
$5.11 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $56,596 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $53,651 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.1241: Reduce excessive boiler blowdown | $3,854 | $4,300 | - | - |
$3,261
-
MMBtu
|
$593 | |
| 02 | 2.2414: Use waste heat from hot flue gases to preheat | $17,930 | $20,000 | - | - |
$17,930
-
MMBtu
|
- | |
| 03 | 2.1224: Replace boiler | $27,684 | $150,000 | - | - |
$27,684
-
MMBtu
|
- | |
| 04 | 2.4133: Use most efficient type of electric motors | $199 | $80 |
$102
3,528
kWh
|
$97
-
kW-mo/yr
|
- | - | |
| 05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $499 | $400 |
$289
7,235
kWh
|
$210
-
kW-mo/yr
|
- | - | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,139 | $1,364 |
$1,312
45,171
kWh
|
$827
-
kW-mo/yr
|
- | - | |
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,346 | $1,197 |
$718
24,764
kWh
|
$628
-
kW-mo/yr
|
- | - | |
| 08 | 2.7135: Install occupancy sensors | $906 | $7,407 |
$906
31,198
kWh
|
- | - | - | |
| 09 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $2,039 | $7,405 |
$1,161
40,040
kWh
|
$878
-
kW-mo/yr
|
- | - | |
| TOTAL RECOMMENDED | $56,596 | $192,153 |
$4,488
151,936
kWh
|
$2,640
-
kW-mo/yr
|
$48,875
-
MMBtu
|
$593 | ||
| TOTAL IMPLEMENTED | $53,651 | $177,341 |
$2,421
80,698
kWh
|
$1,762
-
kW-mo/yr
|
$48,875
-
MMBtu
|
$593 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs