Assessment Year | 2003 |
---|---|
Principal Product | Load Cells and Force Measurement Devices |
NAICS | 334515: Instrument Manufacturing for Measuring and Testing Electricity and Electrical Signals |
SIC | 3825: Instruments for Measuring and Testing of Electricity and Electrical Signals |
Sales Range | $10 M to 50M |
# of Employees | 80 |
Plant Area |
20,000
ft2
|
Annual Production | 0
units
|
Production Hrs. Annual | 5,035
hrs
|
Location (State) | Arizona |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $60,140 | 812,800 |
kWh
|
$0.074 |
Electricity Demand | $3,429 | 2,124 |
kW-mo/yr
|
$1.61 |
Electricity Fees | $4,437 | - |
|
- |
Natural Gas | $334 | 7 |
MMBtu
|
$47.71 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $16,021 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $2,035 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,103 | $9,525 |
$1,456
29,119
kWh
|
$647
-
kW-mo/yr
|
- | |
02 | 2.7111: Reduce illumination to minimum necessary levels | $1,258 | $136 |
$1,042
6,732
kWh
|
$216
-
kW-mo/yr
|
- | |
03 | 2.7135: Install occupancy sensors | $756 | $825 |
$756
16,583
kWh
|
- | - | |
04 | 2.6218: Turn off equipment when not in use | $779 | - |
$779
17,094
kWh
|
- | - | |
05 | 2.7232: Replace existing hvac unit with high efficiency model | $1,918 | $4,500 |
$1,607
35,249
kWh
|
$311
-
kW-mo/yr
|
- | |
06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $117 | $60 |
$88
1,931
kWh
|
$29
-
kW-mo/yr
|
- | |
07 | 2.4314: Use synthetic lubricant | $352 | $174 |
$49
1,072
kWh
|
$12
-
kW-mo/yr
|
$291 | |
08 | 2.4231: Reduce the pressure of compressed air to the minimum required | $8,467 | $1,500 |
$6,887
151,025
kWh
|
$1,580
-
kW-mo/yr
|
- | |
09 | 2.4226: Use / purchase optimum sized compressor | $271 | $430 |
$54
1,188
kWh
|
$217
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $16,021 | $17,150 |
$12,718
259,993
kWh
|
$3,012
-
kW-mo/yr
|
$291 | ||
TOTAL IMPLEMENTED | $2,035 | $4,560 |
$1,695
37,180
kWh
|
$340
-
kW-mo/yr
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs