ITAC Assessment: AS0326
ITAC logo
ITAC Assessment: AS0326
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2002
Principal Product Manufactures and Installs aluminum windows, dorrs, and tempered glass pr
NAICS
n/a
SIC 3442: Metal Doors, Sash, Frames, Molding, and Trim Manufacturing
Sales Range $10
M
to 50
M
# of Employees 174
Plant Area 71,000
ft2
Annual Production 198,000
pieces
Production Hrs. Annual 5,313
hrs
Location (State) Nevada

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $69,121 920,950
kWh
Electricity Demand $6,971 2,403
kW-mo/yr
Electricity Fees $5,357 -
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $89,555 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $27,817 $100 n/a $25,447
310,174
kWh
$2,370
-
kW-mo/yr
- - - -
02 2.1311: Replace electrically-operated equipment with fossil fuel equipment $1,641 $1,600 n/a $2,125
25,901
kWh
$179
-
kW-mo/yr
$(-663.0)
-
MMBtu
- - -
03 2.4231: Reduce the pressure of compressed air to the minimum required $1,936 - n/a $1,936
23,600
kWh
- - - - -
04 4.111: Add equipment/ operators to reduce production bottleneck $11,799 $489 n/a $164
2,000
kWh
$14
-
kW-mo/yr
- $9,082 - $2,539
05 4.446: Automate finishing process $23,920 $582 n/a - - - $23,920 - -
06 4.111: Add equipment/ operators to reduce production bottleneck $10,080 $750 n/a - - - $10,080 - -
07 4.514: Re-arrange equipment layout to reduce handling costs $12,362 $100 n/a - - - - $12,362 -
TOTAL RECOMMENDED $89,555 $3,621 $29,672
361,675
kWh
$2,563
-
kW-mo/yr
$(-663.0)
-
MMBtu
$43,082 $12,362 $2,539
TOTAL IMPLEMENTED - - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs