Assessment Year | 2002 |
---|---|
Principal Product | Manufactures and Installs aluminum windows, dorrs, and tempered glass pr |
NAICS |
n/a
|
SIC | 3442: Metal Doors, Sash, Frames, Molding, and Trim Manufacturing |
Sales Range | $10 M to 50M |
# of Employees | 174 |
Plant Area |
71,000
ft2
|
Annual Production | 198,000
pieces
|
Production Hrs. Annual | 5,313
hrs
|
Location (State) | Nevada |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $69,121 | 920,950 |
kWh
|
$0.075 |
Electricity Demand | $6,971 | 2,403 |
kW-mo/yr
|
$2.90 |
Electricity Fees | $5,357 | - |
|
- |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $89,555 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $27,817 | $100 | n/a |
$25,447
310,174
kWh
|
$2,370
-
kW-mo/yr
|
- | - | - | - |
02 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $1,641 | $1,600 | n/a |
$2,125
25,901
kWh
|
$179
-
kW-mo/yr
|
$(-663.0)
-
MMBtu
|
- | - | - |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,936 | - | n/a |
$1,936
23,600
kWh
|
- | - | - | - | - |
04 | 4.111: Add equipment/ operators to reduce production bottleneck | $11,799 | $489 | n/a |
$164
2,000
kWh
|
$14
-
kW-mo/yr
|
- | $9,082 | - | $2,539 |
05 | 4.446: Automate finishing process | $23,920 | $582 | n/a | - | - | - | $23,920 | - | - |
06 | 4.111: Add equipment/ operators to reduce production bottleneck | $10,080 | $750 | n/a | - | - | - | $10,080 | - | - |
07 | 4.514: Re-arrange equipment layout to reduce handling costs | $12,362 | $100 | n/a | - | - | - | - | $12,362 | - |
TOTAL RECOMMENDED | $89,555 | $3,621 |
$29,672
361,675
kWh
|
$2,563
-
kW-mo/yr
|
$(-663.0)
-
MMBtu
|
$43,082 | $12,362 | $2,539 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs