| Assessment Year | 2001 |
|---|---|
| Principal Product | Sheet metal fabrication, powder metal coatings |
| NAICS |
n/a
|
| SIC | 3444: Sheet Metal Work |
| Sales Range | $1 M to 5M |
| # of Employees | 40 |
| Plant Area |
40,000
ft2
|
| Annual Production | 60,000
pieces
|
| Production Hrs. Annual | 3,000
hrs
|
| Location (State) | Arizona |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $29,930 | 334,680 |
kWh
|
$0.089 |
| Electricity Demand | $3,017 | 1,830 |
kW-mo/yr
|
$1.65 |
| Electricity Fees | $2,374 | - |
|
- |
| Natural Gas | $45,790 | 6,445 |
MMBtu
|
$7.10 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $196,505 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $105,685 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $895 | $120 |
$621
8,374
kWh
|
$274
-
kW-mo/yr
|
- | - | - | |
| 02 | 2.7145: Install skylights | $1,241 | $1,992 |
$1,241
16,740
kWh
|
- | - | - | - | |
| 03 | 2.1121: Use insulation in furnaces to facilitate heating / cooling | $764 | $2,484 | - | - |
$764
-
MMBtu
|
- | - | |
| 04 | 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary | $5,488 | $648 |
$4,280
57,750
kWh
|
$1,208
-
kW-mo/yr
|
- | - | - | |
| 05 | 4.513: Re-arrange equipment layout to reduce labor costs | $64,704 | $8,580 | - | - | - | $64,704 | - | |
| 06 | 4.446: Automate finishing process | $58,240 | $688 | - | - | - | $58,240 | - | |
| 07 | 4.811: Demolish old building to reduce tax and insurance bills | $29,680 | $438 | - | - | - | - | $29,680 | |
| 08 | 4.111: Add equipment/ operators to reduce production bottleneck | $19,493 | $294 |
$1,536
20,728
kWh
|
- | - | $17,957 | - | |
| 09 | 4.711: Initiate a total quality management program | $16,000 | $3,940 | - | - | - | - | $16,000 | |
| TOTAL RECOMMENDED | $196,505 | $19,184 |
$7,678
103,592
kWh
|
$1,482
-
kW-mo/yr
|
$764
-
MMBtu
|
$140,901 | $45,680 | ||
| TOTAL IMPLEMENTED | $105,685 | $13,462 |
$5,816
78,478
kWh
|
$1,208
-
kW-mo/yr
|
- | $82,661 | $16,000 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | One-time Revenue or Avoided Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs