Assessment Year | 2000 |
---|---|
Principal Product | Mobile Tanker for Fuel or Water |
NAICS |
n/a
|
SIC | 3443: Fabricated Plate Work (Boiler Shops) |
Sales Range | $10 M to 50M |
# of Employees | 128 |
Plant Area |
60,000
ft2
|
Annual Production | 720
pieces
|
Production Hrs. Annual | 5,202
hrs
|
Location (State) | Arizona |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $75,549 | 864,009 |
kWh
|
$0.087 |
Electricity Demand | $4,145 | 2,467 |
kW-mo/yr
|
$1.68 |
Electricity Fees | $4,898 | - |
|
- |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $192,377 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $8,590 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (non-haz) Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings | By-product Production Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,680 | $3,360 |
$1,132
24,033
kWh
|
$548
-
kW-mo/yr
|
- | - | - | - | - | - | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $643 | $180 |
$407
8,499
kWh
|
$236
-
kW-mo/yr
|
- | - | - | - | - | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,040 | $120 |
$2,178
46,014
kWh
|
$862
-
kW-mo/yr
|
- | - | - | - | - | - | |
04 | 2.7261: Install timers and/or thermostats | $815 | $450 |
$815
17,292
kWh
|
- | - | - | - | - | - | - | |
05 | 2.7232: Replace existing hvac unit with high efficiency model | $3,296 | $6,000 |
$2,395
50,703
kWh
|
$901
-
kW-mo/yr
|
- | - | - | - | - | - | |
06 | 2.4133: Use most efficient type of electric motors | $1,134 | $2,590 |
$933
19,637
kWh
|
$201
-
kW-mo/yr
|
- | - | - | - | - | - | |
07 | 2.4314: Use synthetic lubricant | $2,736 | $1,585 |
$383
8,206
kWh
|
$203
-
kW-mo/yr
|
$870
-
gal
|
- | - | - | $1,280 | - | |
08 | 3.5217: Reuse / recycle/ sell paper products | $1,262 | $120 | - | - | - | - | - | $(-682.0) | - | $1,944 | |
09 | 3.5316: Contract a wood pallet recycling company | $588 | $60 | - | - | - |
$588
-
lb
|
- | - | - | - | |
10 | 4.651: Install back-up equipment | $103,995 | $14,000 | - | - | - | - | $103,995 | - | - | - | |
11 | 4.431: Train operators for maximum operating efficiency | $73,188 | $38,400 | - | - | - | - | $73,188 | - | - | - | |
TOTAL RECOMMENDED | $192,377 | $66,865 |
$8,243
174,384
kWh
|
$2,951
-
kW-mo/yr
|
$870
-
gal
|
$588
-
lb
|
$177,183 | $(-682.0) | $1,280 | $1,944 | ||
TOTAL IMPLEMENTED | $8,590 | $7,655 |
$4,626
97,890
kWh
|
$1,814
-
kW-mo/yr
|
$870
-
gal
|
- | - | - | $1,280 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (non-haz) Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings | By-product Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs