ITAC Assessment: AS0290
ITAC logo
ITAC Assessment: AS0290
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product Mobile Tanker for Fuel or Water
NAICS
n/a
SIC 3443: Fabricated Plate Work (Boiler Shops)
Sales Range $10
M
to 50
M
# of Employees 128
Plant Area 60,000
ft2
Annual Production 720
pieces
Production Hrs. Annual 5,202
hrs
Location (State) Arizona

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $75,549 864,009
kWh
Electricity Demand $4,145 2,467
kW-mo/yr
Electricity Fees $4,898 -
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $192,377 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $8,590

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Other Liquid (non-haz) Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings By-product Production Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $1,680 $3,360 $1,132
24,033
kWh
$548
-
kW-mo/yr
- - - - - -
02 2.4231: Reduce the pressure of compressed air to the minimum required $643 $180 $407
8,499
kWh
$236
-
kW-mo/yr
- - - - - -
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,040 $120 $2,178
46,014
kWh
$862
-
kW-mo/yr
- - - - - -
04 2.7261: Install timers and/or thermostats $815 $450 $815
17,292
kWh
- - - - - - -
05 2.7232: Replace existing hvac unit with high efficiency model $3,296 $6,000 $2,395
50,703
kWh
$901
-
kW-mo/yr
- - - - - -
06 2.4133: Use most efficient type of electric motors $1,134 $2,590 $933
19,637
kWh
$201
-
kW-mo/yr
- - - - - -
07 2.4314: Use synthetic lubricant $2,736 $1,585 $383
8,206
kWh
$203
-
kW-mo/yr
$870
-
gal
- - - $1,280 -
08 3.5217: Reuse / recycle/ sell paper products $1,262 $120 - - - - - $(-682.0) - $1,944
09 3.5316: Contract a wood pallet recycling company $588 $60 - - - $588
-
lb
- - - -
10 4.651: Install back-up equipment $103,995 $14,000 - - - - $103,995 - - -
11 4.431: Train operators for maximum operating efficiency $73,188 $38,400 - - - - $73,188 - - -
TOTAL RECOMMENDED $192,377 $66,865 $8,243
174,384
kWh
$2,951
-
kW-mo/yr
$870
-
gal
$588
-
lb
$177,183 $(-682.0) $1,280 $1,944
TOTAL IMPLEMENTED $8,590 $7,655 $4,626
97,890
kWh
$1,814
-
kW-mo/yr
$870
-
gal
- - - $1,280 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Other Liquid (non-haz) Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings By-product Production Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs