ITAC Assessment: AS0280
ITAC logo
ITAC Assessment: AS0280
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product Plastic Products
NAICS
n/a
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 60
Plant Area 78,000
ft2
Annual Production 1,485,000
lb
Production Hrs. Annual 8,400
hrs
Location (State) Arizona

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $257,245 4,085,287
kWh
Electricity Demand $57,224 7,975
kW-mo/yr
Electricity Fees $29,127 -
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $391,632 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $37,059

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Water Disposal Savings Solid Waste (non-haz) Savings Administrative Changes Savings Primary Raw Material Savings Increase in Production Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $15,109 $12,163 $12,881
186,987
kWh
$2,228
-
kW-mo/yr
- - - - -
02 2.7135: Install occupancy sensors $1,996 $2,925 $1,699
22,567
kWh
$297
-
kW-mo/yr
- - - - -
03 2.7121: Utilize daylight whenever possible in lieu of artificial light $2,658 $1,605 $2,182
31,946
kWh
$476
-
kW-mo/yr
- - - - -
04 2.7232: Replace existing hvac unit with high efficiency model $16,673 $30,000 $14,577
212,485
kWh
$2,096
-
kW-mo/yr
- - - - -
05 2.4133: Use most efficient type of electric motors $1,337 $1,066 $1,164
16,999
kWh
$173
-
kW-mo/yr
- - - - -
06 2.4231: Reduce the pressure of compressed air to the minimum required $1,719 $60 $1,416
20,809
kWh
$303
-
kW-mo/yr
- - - - -
07 2.4221: Install compressor air intakes in coolest locations $683 $220 $597
8,792
kWh
$86
-
kW-mo/yr
- - - - -
08 2.2511: Insulate bare equipment $995 $378 $995
15,533
kWh
- - - - - -
09 3.4156: Use flow control valves on equipment to optimize water use $287 $60 - - $995
-
Tgal
- $(-708.0) - -
10 3.6192: Use a less expensive method of waste removal $444 $60 - - - $444
-
lb
- - -
11 3.6192: Use a less expensive method of waste removal $697 $60 - - - $697
-
lb
- - -
12 4.126: Install sensors to detect defects $136,234 $16,000 $(-6,753.0)
(-98,476)
kWh
$(-1,013.0)
-
kW-mo/yr
- - - $144,000 -
13 4.113: Install refrigeration system to cool product $212,800 $30,000 - - - - - - $212,800
TOTAL RECOMMENDED $391,632 $94,597 $28,758
417,642
kWh
$4,646
-
kW-mo/yr
$995
-
Tgal
$1,141
-
lb
$(-708.0) $144,000 $212,800
TOTAL IMPLEMENTED $37,059 $45,272 $31,799
463,950
kWh
$4,973
-
kW-mo/yr
$995
-
Tgal
- $(-708.0) - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Water Disposal Savings Solid Waste (non-haz) Savings Administrative Changes Savings Primary Raw Material Savings Increase in Production Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs