Assessment Year | 2000 |
---|---|
Principal Product | Plastic Products |
NAICS |
n/a
|
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 60 |
Plant Area |
78,000
ft2
|
Annual Production | 1,485,000
lb
|
Production Hrs. Annual | 8,400
hrs
|
Location (State) | Arizona |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $257,245 | 4,085,287 |
kWh
|
$0.063 |
Electricity Demand | $57,224 | 7,975 |
kW-mo/yr
|
$7.18 |
Electricity Fees | $29,127 | - |
|
- |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $391,632 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $37,059 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Primary Raw Material Savings | Increase in Production Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $15,109 | $12,163 |
$12,881
186,987
kWh
|
$2,228
-
kW-mo/yr
|
- | - | - | - | - | |
02 | 2.7135: Install occupancy sensors | $1,996 | $2,925 |
$1,699
22,567
kWh
|
$297
-
kW-mo/yr
|
- | - | - | - | - | |
03 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $2,658 | $1,605 |
$2,182
31,946
kWh
|
$476
-
kW-mo/yr
|
- | - | - | - | - | |
04 | 2.7232: Replace existing hvac unit with high efficiency model | $16,673 | $30,000 |
$14,577
212,485
kWh
|
$2,096
-
kW-mo/yr
|
- | - | - | - | - | |
05 | 2.4133: Use most efficient type of electric motors | $1,337 | $1,066 |
$1,164
16,999
kWh
|
$173
-
kW-mo/yr
|
- | - | - | - | - | |
06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,719 | $60 |
$1,416
20,809
kWh
|
$303
-
kW-mo/yr
|
- | - | - | - | - | |
07 | 2.4221: Install compressor air intakes in coolest locations | $683 | $220 |
$597
8,792
kWh
|
$86
-
kW-mo/yr
|
- | - | - | - | - | |
08 | 2.2511: Insulate bare equipment | $995 | $378 |
$995
15,533
kWh
|
- | - | - | - | - | - | |
09 | 3.4156: Use flow control valves on equipment to optimize water use | $287 | $60 | - | - |
$995
-
Tgal
|
- | $(-708.0) | - | - | |
10 | 3.6192: Use a less expensive method of waste removal | $444 | $60 | - | - | - |
$444
-
lb
|
- | - | - | |
11 | 3.6192: Use a less expensive method of waste removal | $697 | $60 | - | - | - |
$697
-
lb
|
- | - | - | |
12 | 4.126: Install sensors to detect defects | $136,234 | $16,000 |
$(-6,753.0)
(-98,476)
kWh
|
$(-1,013.0)
-
kW-mo/yr
|
- | - | - | $144,000 | - | |
13 | 4.113: Install refrigeration system to cool product | $212,800 | $30,000 | - | - | - | - | - | - | $212,800 | |
TOTAL RECOMMENDED | $391,632 | $94,597 |
$28,758
417,642
kWh
|
$4,646
-
kW-mo/yr
|
$995
-
Tgal
|
$1,141
-
lb
|
$(-708.0) | $144,000 | $212,800 | ||
TOTAL IMPLEMENTED | $37,059 | $45,272 |
$31,799
463,950
kWh
|
$4,973
-
kW-mo/yr
|
$995
-
Tgal
|
- | $(-708.0) | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Primary Raw Material Savings | Increase in Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs