ITAC Assessment: AS0273
ITAC logo
ITAC Assessment: AS0273
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product Vinyl Windows & Doors
NAICS
n/a
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $1
M
to 5
M
# of Employees 33
Plant Area 40,000
ft2
Annual Production 18,000
pieces
Production Hrs. Annual 2,201
hrs
Location (State) Arizona

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $7,266 110,199
kWh
Electricity Demand $1,254 508
kW-mo/yr
Electricity Fees $939 -
Natural Gas $512 37
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $20,294 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Administrative Changes Savings One-time Revenue or Avoided Cost Savings
01 2.7133: Use separate switches on perimeter lighting which may be turned off when natural light is available $948 $920 $948
16,706
kWh
- - - -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,057 $120 $675
12,016
kWh
$382
-
kW-mo/yr
- - -
03 2.7261: Install timers and/or thermostats $157 $150 $157
2,931
kWh
- - - -
04 2.7232: Replace existing hvac unit with high efficiency model $470 $1,000 $387
6,741
kWh
$83
-
kW-mo/yr
- - -
05 3.6192: Use a less expensive method of waste removal $3,780 $60 - - $3,780
-
lb
- -
06 3.5313: Increase amount of waste recovered for resale $3,270 $120 - - $3,270
-
lb
- -
07 4.812: Apply for investment incentives $137 $60 - - - $94 $43
08 4.511: Expand operations into unused space $10,475 $3,200 - - - $10,475 -
TOTAL RECOMMENDED $20,294 $5,630 $2,167
38,394
kWh
$465
-
kW-mo/yr
$7,050
-
lb
$10,569 $43
TOTAL IMPLEMENTED - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Administrative Changes Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs